November 25th, 2024
Holly Williams, Chair
Pikes Peak Rural Transportation Authority
15 South 7th Street
Colorado Springs, CO 80905
RE: 2024 3rd Quarter Report, City of Manitou Springs
Dear Chair Holly Williams:
In the third quarter of 2024, the City of Manitou Springs utilized Pikes Peak Rural Transportation Authority (PPRTA) funding as follows:
Maintenance Funds:
The City developed the 2024 surface improvement project and accepted Pyramid Construction Inc’s $777,456.20 bid proposal after the City went to bid. The project will completely utilize the 2024 maintenance allocation as well as local funds in addition. Up-to-date, the City has spent $354,158.00 with the remainder of the project ($423,298.20) being paid in Q4. $79,742.00 has been spent on this project since Q2 Report.
Manitou Springs Priority “A” Projects:
Transit Shuttle Parking
Total project cost: $2M+
Expended: $300,846 on partial demolition, site stability, Survey and design
Status: Working to develop the mobility hub, plaza conceptual plans, and bathrooms
$8,191.76 were expended on this project since last report. The project is still being discussed and options explored.
Downtown Sidewalk, Drainage and Utilities Improvements
Total program budget: $292,616
Expended/encumbered: $125,000
No funds were expended on this project.
Manitou Ave W. End Ped & Drainage Improvements
Total project cost: $4M (82% Federally Funded – 18% PPRTA Funded)
Expended: $877,340
No funds were expended on this project.
With Regards,
Joshua Radey
Sr. GIS Specialist
City of Manitou Springs