September 4th, 2024
Jim Godfrey, Chair
Pikes Peak Rural Transportation Authority
15 South 7th Street
Colorado Springs, CO 80905
RE: 2024 2nd Quarter Report, City of Manitou Springs
Dear Chair Godfrey:
In the second quarter of 2024, the City of Manitou Springs utilized Pikes Peak Rural Transportation Authority (PPRTA) funding as follows:
Maintenance Funds:
The City developed the 2024 surface improvement project and accepted Pyramid Construction Inc’s $777,456.20 bid proposal after the City went to bid. The project will completely utilize the 2024 maintenance allocation as well as local funds in addition. Up-to-date, the City has spent $274,416.00 for the 2” milling and overlay portion of the project. We are currently completing the cape seal portion of the project and will spend another $503,040.20 to complete the 2024 surface improvement project contract with Pyramid Construction Inc.
Manitou Springs Priority “A” Projects:
Transit Shuttle Parking
Total project cost: $2M+
Expended: $292,655 on partial demolition, site stability, and design
Status: Working to develop the mobility hub, plaza conceptual plans, and bathrooms
$23,655.00 were expended on this project since last report. The project is still being discussed and options explored.
Downtown Sidewalk, Drainage and Utilities Improvements
Total program budget: $292,616
Expended/encumbered: $125,000
No funds were expended on this project.
Manitou Ave W. End Ped & Drainage Improvements
Total project cost: $4M (82% Federally Funded – 18% PPRTA Funded)
Expended: $877,340
$2,340.00 were expended on this project since last report.
With Regards,
Andrew Morren
City Engineer
City of Manitou Springs