Project Description
Intersection improvements at the intersection of Security Boulevard & Main Street. The intersections are currently equipped with traffic control devices that are more than three decades old with leaning traffic poles, inadequate signal head clearance, and exposed cabling. Improvements will include the installation of new traffic signals and accompanying equipment, as well as new signage, striping, and pedestrian improvements. Improvements will update intersection operational efficiency, increase pedestrian and ADA access, and increase overall public safety.
Team
- Designer: El Paso County Engineering
- Contractor: Sturgeon Electric Inc.
- CM: FHU Engineering
Cost Summary
- PPRTA Budget: $750,000
Schedule Summary
- Design: 2019 to 2021
- Construction: 2023
Progress / Status
- Advertised 4th Quarter 2022, began construction
- Construction substantially complete (100% work complete, beginning closeout process)
- Closeout will be fully completed upon completion of Security/Widefield & Fontaine Intersection Project as the two Projects were combined for Construction.
- Ongoing coordination with CSU Electric for re-route of overhead electric related to new setup of traffic signal poles – reduction in overhead (OHE) lines to accommodate shift to underground.

Vicinity Map

New Signal Poles and Roadway at Security & Main Intersection
