El Paso County 2024 Third Quarter Report – Project Schedule Projections

A chart showing the design and construction schedules and projections for El Paso County's PPRTA projections in the third quarter of 2024

Title

Project Schedule Projections

Alternate Text

A chart showing the design and construction schedules and projections for El Paso County’s PPRTA projections in the third quarter of 2024

Text Version

The chart shows the project schedule projections for El Paso County’s PPRTA projects as of the third quarter of 2024.

  1. Beacon Lite Road: Highway 105 to County Line
    • Design: Quarter one of 2021 through quarter three of 2024
    • Construction: Quarter four of 2024 and entire year of 2025
  2. Black Forest Road Roadway Improvements: Woodmen Road to Research Parkway
    • City of Colorado Springs Led Project
  3. Deer Creek, Base Camp, Emigrant: Monument Hill to Woodmoor
    • Design: Quarter one of 2021 through quarter four of 2024
    • Construction: 2025 calendar year
  4. Eastonville Road: McLaughlin to Latigo
    • Design: Quarter one of 2021 through quarter one of 2025
    • Construction: 2025 calendar year
  5. Fontaine Boulevard at Security Boulevard and Widefield Boulevard
    • Design: Quarter one of 2021 through quarter one of 2022
    • Construction: Quarter two of 2022 through quarter four of 2024
  6. Highway 105:
    • Interstate 25 to Lake Woodmoor
      • Design: First quarter of 2021 through first quarter of 2023
      • Construction: Second quarter of 2023 through first quarter of 2025
    • Lake Woodmoor to Highway 83
      • Design: Quarter one of 2021 through quarter two of 2025
      • Construction: Third and fourth quarters of 2025
  7. Main Street at Security Boulevard: Complete
  8. Meridian / McLaughlin Roundabout: Complete
  9. Mesa Ridge Parkway Improvements: Powers Boulevard to Marksheffel Road
    • Design: Second quarter of 2021 through fourth quarter of 2023
    • Construction: First quarter of 2024 through fourth quarter of 2025
  10. Monument Hill Road: County Line Road to Woodmoor Road: Complete
  11. New Meridian at U.S. Highway 24: Substantially Complete
  12. South Academy Boulevard: Interstate 25 to Bradley Road Ramps
    • Design: First quarter of 2021 through second quarter of 2023
    • Construction: Third quarter of 2023 through fourth quarter of 2025
  13. Stapleton Drive / Briargate Boulevard Corridor Study (Joint Project)
    • Corridor Study: First quarter of 2021 through fourth quarter of 2023
  14. Tutt Boulevard Extension: Dublin Boulevard to Templeton Gap Road (Joint Project)
    • City of Colorado Springs Led Project
  15. West Colorado Avenue Reconstruction: 31st Street to U.S. Highway 24 (Joint Project): Complete