Project Description
The Highway 105 project will evaluate, design and construct capacity and safety improvements between the I-25 off ramps and SH 83. The corridor is approximately five miles in length and improvements will be phased as required. The corridor study completed in 2012 and subsequent traffic study updates have identified the recommended improvements, prioritized phasing and completed conceptual cost estimates for each phase. For planning purposes, the corridor was broken into 5 segments:
- Project A: I-25 off Ramp to Lake Woodmoor Drive
- Project B: Lake Woodmoor Drive to Martingale Road
- Projects C-E: Martingale Road to SH 83
PPRTA funding is allocated for design and construction of Projects A and B. Project A also has federal funds and is under construction. El Paso County continues active pursuit of funding for the remainder of the corridor from Martingale Drive to SH83. The phasing of construction of future improvements continues to be evaluated.
Project Team
- Designer: HDR
- Construction Management (Project A): Wilson & Company
- Construction (Project A): Wildcat Const.
Cost Summary
- PPRTA Total Budget – $30,416,614
- Design Contracts Authorized – $5,395,122
- Construction Contract Authorized – $14,632,972
- Federal Funds for Project A (Construction) –
- $9,164,527 ($7,982,802 fed / $1,181,725 local)
Schedule Summary
- Conceptual design complete – 2012 (funded by EPC)
- Preliminary corridor design – 2015 to 2018
- Project A – Construction July 2023-2025
- Project B – Design 2021-2025,
- Construction anticipated to begin in 2025
Project Status
- Project A: construction
- Design for Project B is in progress

Vicinity Map

Project A: Bottom Mat North Side

Project A: Top Mat Asphalt North Side