El Paso County 2024 Third Quarter Report – El Paso County Capital Program Projections – “A” List (2015 – 2024)

Project NumberProject NameProject StatusPrevious Funding to Date2024 Budget & Projected Future Allocations: 20222024 Budget & Projected Future Allocations: 20232024 Budget & Projected Future Allocations: 20242024 Budget & Projected Future Allocations: 20253Projected Total Project Cost1Original Budget Estimate2Projected Increase / (Decrease)
1Beacon Lite Road: Hwy 105 to County LineDesign$11,361,000$6,639,000$4,400,000$22,400,000$4,361,000$18,039,000
2Black Forest Rroad Roadway Improvements: Woodmen to Research (Joint Project – City Led)4Design$0$0$3,534,000(3,354,000)
3Deer Creek, Base Camp, Emigrant: Monument Hill to WoodmoorDesign$1,000,000$1,000,000$4,000,000$267,000$6,267,000$200,000$6,067,000
4Eastonville Road: McLaughlin to Latigo6Design$5,659,968$3,285,032$6,455,000$15,400,000$8,525,000$6,875,000
5Fontaine Boulevard at Security Boulevard and Widefield BoulevardConstruction$1,500,000$1,500,000$1,250,000$250,000
6Highway 105: Interstate 25 to State Highway 835Design & Construction$30,416,614$18,438,972$45,000,000$68,305,632$18,314,000$49,991,632
7Main Street at Security BoulevardSubstantially Complete$750,000$750,000$750,000$0
8Meridian / McLaughlin RoundaboutComplete$5,226,000$5,226,000$2,376,000$2,850,000
9Mesa Ridge Parkway Improvements: Powers to MarksheffelDesign$10,014,997$10,014,997$9,975,000$39,997
10Monument Hill Road: County Line Road to Woodmoor DriveComplete$5,183,852$5,183,852$3,965,000$1,218,852
11New Meridian at US 24Complete$4,608,000$4,608,000$4,608,000$0
12South Academy Boulevard: Interstate 25 to Bradley Road RampsConstruction$28,206,924$19,332,370$19,500,000$67,039,294$18,000,000$49,039,294
13Stapleton Drive / Briargate Boulevard Corridor Study (Joint Project – County Led)3Study$314,000$16,040$330,040$314,000$16,040
14West Colorado Avenue Reconstruction: 31st Street to US 24 (Joint Project – County Led)4Complete$18,163,656$30,000$18,193,656$3,428,000$14,765,656
15Tutt Boulevard Extension: Dublin to Templeton Gap Road (Joint Project – City Led)Design$555,000$1,100,000$1,655,000$555,000$2,210,000
Total Capital Projects$122,960,011$23,617,402$36,649,012$24,197,000$0$226,873,471$80,155,000$147,828,471
Conversative Revenue Projections$21,400,556$22,000,000$22,000,000$2,235,007Total Revenue Projection$190,595,574
“A” List & Contingency / “B” List Funds by Year(2,216,846)(14,649,012)-$2,197,000$2,235,007A List & Contingency / “B” List7-$14,611,055
Optimistic Revenue Projections$21,400,556$22,042,573$22,703,850$2,302,057Total Revenue Projection$191,409,047
“A” List & Contingency / “B” List Funds by Year(2,216,846)-$14,606,439-$1,493,150$2,302,057A List & Contingency / “B” List7-$13,797,532
  1. Total Project Cost less other funding sources.
  2. Original 2012 El Paso County Program Revenue Projection at $107 million; member governments used 75% of revenue projections for programming purposes. The remaining 25% of revenue projections planned to be used for contingency, inflation, unexpected costs / scope, and variability in project cost due to early estimating.
  3. 2025 Projected Revenues are distribution of 2015-2024 PPRTA Reserves
  4. El Paso County advanced $7,771,230 to Colorado Springs for West Colorado Avenue and this advance is expected to offset El Paso County allocation and additional Colorado Springs costs for Black Forest Road joint project.
  5. Highway 105 scope for budget is Interstate 25 to Martingale Drive. Remaining preliminary corridor estimate at $65.5 million.
  6. Eastonville Road scope for budget is Stapleton Drive to Rex Road. Remaining preliminary corridor estimate at $25 million.
  7. Remaining Projected Revenues to be used for additional scope for Highway 105, Eastonville Road or PPRTA “B” List.