El Paso County 2024 Third Quarter Report – Eastonville Road Improvement Project

Project Description

The Traffic Impact Study and conceptual design for the corridor identified potential improvements between McLaughlin Road and Latigo Boulevard. Further analysis prioritized the proposed phasing approach and identified Phase I as the priority within the available budget. Current PPRTA budget is allocated for final design and construction of Phase I, along with design of Phase II. El Paso County has postured future PPRTA funding for construction Phase II.  Portions of Phase III will be developer-led with coordination underway.

Team

  • Traffic Impact Study:  Wilson & Company
  • Design: Stanley Consultants

Cost Summary

  • PPRTA budget: $ 15,400,000 (Total Project) with an additional $4,000,000 allocated during Mid-Year Budget Amendment for Reimbursement Agreement for Developer-led Phase III
  • Design Contract: $1,557,929 (Phase I & II, Task Order for additional support)

Schedule Summary

  • Traffic Impact Study: Approved/Accepted March 2021
  • Design:
    • Phase I – 2022-2024: Phase includes Motley Road to Londonderry Drive, with developer support/reimbursement agreement for improvements Londonderry Drive to Rex Road
    • Phase II – 2024-2025: Phase includes McLaughlin Road to Motley Road
  • Construction:
    • Phase I – Anticipated Early 2025
    • Phase II – Following Phase I in late 2025/2026

Progress / Status

  • Phase I Conceptual Design Workshop – 2nd Quarter 2022
  • Phase I Preliminary Design/FIR – 4th Quarter 2022                          
  • Phase I Final Design/FOR – 3rd Quarter 2023
  • Motley Intersection added to Phase I Design – 4th Quarter 2023/1st Quarter 2024
  • Phase I Full Scope Final Design & Property Acquisition – 3rd/4th Quarter 2024
  • Phase II Conceptual Design Workshop – 1st Quarter 2024
  • Phase II Preliminary Design/FIR – 3rd Quarter 2024
  • Phase II FOR – 4th Quarter 2024
  • Phase III (developer-led portion) – Reimbursement Agreement -4th Quarter 2024
Map showing the vicinity and phasing of the Eastonville Road corridor improvement project

Vicinity/Phase Map