El Paso County 2024 Third Quarter Report – Capital Program PPRTA Project Summary

The following table summarizes the current project Status.

Project NameProject Status
Beacon Lite RoadDesign Complete; Finalizing Property Acquisition — 98%
Black Forest Road (Joint w/ City of Colorado Springs)City-led Project
Deer Creek, Base Camp, Microscope Way (aka Emigrant)Design — near 100% (original scope & added RAB)
Eastonville RoadDesign — Phase I — near 100%
Phase II — 60%
Phase III — near 100%
Fontaine Blvd/Security Blvd/Widefield Blvd IntersectionConstruction
85%
Highway 105 Project A — Interstate 25 to Lake Woodmoor DrConstruction – 75%
Highway 105 Project B — Lake Woodmoor to MartingaleDesign — 93%
Highway 105 Project C-E — Martingale to SH83Design — 25%
Main St/Security BlvdConstruction — 100% (Substantial Completion)
Mesa Ridge ParkwayProperty Acquisition
Monument Hill RoadComplete
New Meridian/US 24 Int.Complete
South Academy BlvdConstruction – 45%
Stapleton Drive/Briargate Blvd Corridor Study (joint w/ City of Colorado Springs)Complete
Tutt Blvd Extension (Joint w/ City of Colorado Springs)City-led Project
West Colorado Avenue (joint w/ City of Manitou Springs/City of Colorado Springs)Property Closeout