Project Description
Intersection improvements at Old Meridian Road/US-24, New Meridian Road/US-24 (2014 PPRTA “A” list project); New Meridian Extension from US-24 to Falcon Highway (2004 PPRTA “A” list project), and the Falcon Park & Ride (federal funds project). These projects will be designed and constructed concurrently for cost and time efficiencies. Improvements include removing the traffic signal at Old Meridian/US-24 and converting access control at this location to a right-in/right-out; and completing New Meridian/US-24 as a signalized intersection with adequate turn lanes at all approaches. Improvements will maximize intersection operational efficiency, increase motorist and pedestrian safety and provide appropriate auxiliary lanes and drainage improvements.

Overview of Completed Work
Project Team
- Design: HDR
- CM: Alfred Benesch & Company
- Construction: HEI Civil

Northbound “New” Meridian/Falcon Park & Ride
Cost Summary
- PPRTA budget: $4,608,000 Intersection, $513,411 Meridian Road Extension
Schedule Summary
- Design: Complete
- Construction: Substantially Complete, beginning final acceptance & closeout.
Project Status
- Construction substantially complete, CDOT closeout complete, all permitting closed out. Project reached Final Acceptance in the First Quarter of 2024 and is now complete.
- Substantially complete First Quarter of 2022, Final Acceptance/Closeout in First Quarter of 2024