City of Colorado Springs 2024 Third Quarter Report – PPRTA III – Powers Boulevard Extension: Voyager Bridge over Powers Boulevard

A project status bar showing an indicator arrow approximately two-thirds on the construction phase for the Voyager Bridge over Powers Boulevard

Current Phase: Construction
Construction Percent Complete: 75%
Anticipated Construction Date: Spring 2025

Project Description: The Voyager Bridge over Powers Boulevard project is a part of the overall northern Powers Blvd Extension from SH83 to Voyager Pkwy. It is a PPRTA regional collaborative Priority A project which will connect Powers Blvd with I-25. Powers Blvd currently ends with an at-grade crossing at Voyager Pkwy.

The first portion of the northern Powers Blvd Extension was the completion of the I25 exit ramp (Exit 155) to Voyager Pkwy. The Copper Ridge Metropolitan District, in conjunction with the City and PPRTA, are replacing the at-grade intersection of Powers Blvd and Voyager Pkwy with an interchange which includes a bridge on Voyager Pkwy over Powers Blvd.

Project Location Map

A diagram of the Voyager Bridge on the current and future Powers Boulevard extension.

Figure 38. Bridge Deck

A photo of concrete pumps laying bridge deck on the Voyager Bridge over Powers Boulevard

Figure 39. Bridge Deck

A photo of the finished concrete pour on the Voyager Bridge over Powers Boulevard.

Highlights:

  • Utility relocation complete.
  • Bridge foundation and deck installed.
  • Engineering for future phases of SH83 and Voyager Pkwy extension have started.