Current Phase: Design
Engineering Percent Complete: 75%
Anticipated Construction Date: June 2025
Project Description: This project will make improvements to Dublin Blvd from approximately Peterson Rd to Marksheffel Rd. Improvements include widening the existing roadway from one lane in each direction to two lanes in each direction with a raised median and multi-use shoulders per the City standard section for principal arterial roadways.
Figure 32. Map of project area.

Figure 33. Dublin Blvd and Peterson Rd. looking West

Budget
| Funding Source | Estimated Project Cost1 | Obligated | Spent to Date (Actual) | Percent Spent to Date2 |
|---|---|---|---|---|
| PPRTA III4 | $16,600,000 | $0 | $0 | 0% |
| PPRTA II3 | $1,134,210 | $1,134,210 | $457,397 | 40% |
| Total | $17,734,210 | $1,134,210 | $457,397 | 40% |
- Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
- Actual funds spent of the current obligated amount.
- PPRTA III and CSU funds will be added with a forthcoming CIP
Highlights:
- Consultant completed 60% engineering documents and is currently working towards 90% submittal, which is scheduled for December 2024.
- Coordinated a public meeting to share the plans with the public and subsequently responded to questions received at the meeting.
- Identified utility conflicts and working towards groundwater solution.
- Continued collaborating with Marksheffel Rd team to ensure a seamless transition.