This program constructs drainage improvements needed in advance of roadway rehabilitation or reconstruction efforts.
| Program Categories | 2024 Initial Budget | Carryover Budget | Midyear Adjustment or Line-Item Transfer | 2024 Total Budget | Amount Encumbered / Spent | % |
|---|---|---|---|---|---|---|
| Drainage Improvements | $412,000 | $0 | $0 | $412,000 | $412,000 | 100% |
| Total | $412,000 | $0 | $0 | $412,000 | $412,000 | 100% |
Projects Completed in Q3 2024 and Continuing Efforts:
The following locations will have updated storm pipe lining:
- Broadmoor Hills Drive
- Custer Avenue
- Deliverance Drive
- N Hancock Avenue
- Palmer Park Boulevard
- East Platte Avenue
- Templeton Gap Road
- Vickers Drive