City of Colorado Springs 2024 Third Quarter Report – PPRTA III – A-list Capital Programs – Citywide Intersection Improvements Phase I

Construct improvements at intersections that will reduce delays, improve air quality, and enhance safety for both motorized and non-motorized traffic.

Program Categories2024 Initial BudgetCarryover BudgetMidyear Adjustment or Line-Item Transfer2024 Total BudgetAmount Encumbered / Spent%
Transportation Studies$82,400$82,316$0$164,536$00%
Engineering$164,800$821,356$0$986,156$693,77770%
Safety Projects$288,400$739,220$500,000$1,527,620$127,6968%
Intersection Improvements$288,400$6,570,849$0$6,859,249$5,092,95174%
Total$824,000$8,213,561$500,000$9,537,561$5,914,42462%

Projects Completed in Q3 2024 and Continuing Efforts:

  • Engineering for roundabouts at the Peterson/US24 interchange.
  • Construction of Marksheffel improvement at the Barnes intersection.
  • Engineering for roundabout at the Fontanero/31st Street intersection.
  • Engineering of signal improvements at the Circle Drive/Maizeland Road intersection.