Construct improvements at intersections that will reduce delays, improve air quality, and enhance safety for both motorized and non-motorized traffic.
| Program Categories | 2024 Initial Budget | Carryover Budget | Midyear Adjustment or Line-Item Transfer | 2024 Total Budget | Amount Encumbered / Spent | % |
|---|---|---|---|---|---|---|
| Transportation Studies | $82,400 | $82,316 | $0 | $164,536 | $0 | 0% |
| Engineering | $164,800 | $821,356 | $0 | $986,156 | $693,777 | 70% |
| Safety Projects | $288,400 | $739,220 | $500,000 | $1,527,620 | $127,696 | 8% |
| Intersection Improvements | $288,400 | $6,570,849 | $0 | $6,859,249 | $5,092,951 | 74% |
| Total | $824,000 | $8,213,561 | $500,000 | $9,537,561 | $5,914,424 | 62% |
Projects Completed in Q3 2024 and Continuing Efforts:
- Engineering for roundabouts at the Peterson/US24 interchange.
- Construction of Marksheffel improvement at the Barnes intersection.
- Engineering for roundabout at the Fontanero/31st Street intersection.
- Engineering of signal improvements at the Circle Drive/Maizeland Road intersection.