Current Phase: Construction
Construction Percent Complete: 43%
Anticipated Completion Date: Late 2025/Early 2026
Project Description: Constructed by the Colorado Department of Highways in 1963, the Circle Drive Bridges carry eastbound and westbound lanes of Circle Drive on separate structures. The western pair of bridges cross Fountain Creek. The eastern pair of bridges cross the BNSF Railroad, a Fountain Mutual Irrigation Company conveyance facility, the Hancock Expressway, and East Las Vegas Street. This project will replace the deteriorating structures with four new bridges. The new bridges will have wider cross sections to allow for better pedestrian movement.
Figure 12. Overnight crews pouring concrete for the eastbound Fountain Creek Bridge deck.

Figure 13. Tied reinforcement for the eastbound Fountain Creek Bridge deck.

Budget
| Funding Source | Estimated Project Cost1 | Obligated | Spent to Date (Actual) | Percent Spent to Date2 |
|---|---|---|---|---|
| PPRTA | $45,204,000 | $45,162,127 | $19,143,531 | 42% |
| CSU | $5,288,624 | $3,421,437 | $863,531 | 25% |
| PPRTA Traffic | $913,852 | $913,852 | $0 | 0% |
| Total | $51,406,475 | $49,497,415 | $20,007,062 | 40% |
- Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
- Actual funds spent of the current obligated amount.
Highlights:
- Eastbound Circle bridges girders installed.
- Eastbound Circle bridges concrete deck installed.
- On track for completion and opening of eastbound Circle bridges in Q4 2024.