Capital Project Schedule in the City of Colorado Springs 2024 Third Quarter Report for Capital Projects
Alternate Text for Image Description
Table showing the capital project schedule for Colorado Springs PPRTA projects from 2023 to 2027.
Text Version
This chart shows the project names, if they were completed or the status and schedule for years 2023-27.
- 8th Street Improvements: Motor City Way to Fountain Creek – engineering and right-of-way from first through third quarters of 2024, construction from the fourth quarter of 2024 through the first quarter of 2026.
- Academy Boulevard: Bijou Street to Airport Road pavement reconstruction – construction from the first quarter of 2024 through the second quarter of 2025.
- Academy Boulevard: Fountain Boulevard to Milton Proby Parkway pavement reconstruction – construction from the first quarter of 2024 through the first quarter of 2027.
- Academy Boulevard over Cottonwood Creek bridge placement – complete May 2019.
- Airport Road over Spring Creek bridge replacement – complete June 2022.
- Barnes Road roadway improvements, Solar Ridge Drive to Powers Boulevard – complete May 2019.
- Black Forest Road roadway improvements: Woodmen Road to Research Parkway (joint project) – construction from first through fourth quarters of 2024.
- Centennial Boulevard extension: Fillmore Road to Fontanero Street – complete November 2023.
- Centennial Boulevard: Garden of the Gods Road to Fillmore Street pavement reconstruction – complete October 2017.
- Chestnut Street over South Douglas Creek bridge replacement – complete April 2017.
- Circle Drive bridges – construction first quarter of 2024 through fourth quarter of 2025.
- Dublin Boulevard road improvements: Bridle Pass Way to Powers Boulevard – complete June 2019.
- El Paso Street bridge over Fountain Creek tributary replacement – complete June 2024.
- Enchanted Circle over Sand Creek tributary bridge replacement – complete June 2019.
- Galley Road over Sand Creek bridge replacement – construction first quarter of 2024 through fourth quarter of 2025.
- Interstate 25 ramps: South Nevada Avenue and Tejon Street corridor improvements – construction first quarter of 2024 through second quarter of 2025.
- Las Vegas Street and Royer Street Union Pacific Railroad crossing relocation – engineering and right-of-way in first through third quarters of 2024, construction in fourth quarter of 2024 through fourth quarter of 2025.
- Old Ranch Road improvements and bridge construction – complete November 2015.
- Pikes Peak Avenue: Colorado to Printers Parkway pavement reconstruction – complete November 2019.
- Platte Avenue connection to Interstate 25 study – combined with Platte Avenue Corridor Study.
- Platte Avenue Corridor Study – complete February 2024.
- Platte Avenue westbound over Sand Creek bridge replacement – complete September 2022.
- South Cheyenne Canyon Road 1 over Cheyenne Creek bridge replacement – complete June 2024.
- Shooks Run bridge corridor study – complete February 2017.
- Stapleton Drive / Briargate Boulevard corridor study (joint project) – complete May 2023.
- Tutt Boulevard extension: Dublin Boulevard to Templeton Gap Road (joint project) – engineering and right-of-way in first quarter of 2024, construction in second through fourth quarters of 2024.
- Union Pacific Railroad mainline over Fontanero Street bridge replacement – engineering and right-of-way from first quarter of 2024 through second quarter of 2025, construction from third quarter of 2025 through third quarter of 2027.
- Union Pacific Railroad, Nevada Avenue and Tejon Street crossing reconstruction (design only) – engineering and right-of-way first quarter of 2024 through second quarter of 2025.
- West Colorado Avenue reconstruction: 31st Street to U.S. Highway 24 (joint project) – complete November 2019
- West Fillmore Road over unnamed channel bridge replacement – complete June 2024.
- Woodmen Road improvements: Union Boulevard continuous flow intersection – complete November 2019.