City of Colorado Springs 2024 Second Quarter Report – Capital Program Overview – Figure 3. Project Locations with Current Phase

A map of PPRTA A-list capital projects and their status in the second quarter of 2024

Title

Project Locations with Current Phase in the City of Colorado Springs 2024 Second Quarter Report for Capital Projects

Alternate Text for Image Description

A map of PPRTA A-list capital projects and their status in the second quarter of 2024

Text Version

The map shows the locations of 30 projects in the City of Colorado Springs funded by PPRTA-2, with a status icon on each project indicating complete, under construction, in engineering and in the future.

IDDESCRIPTIONSTATUS
18TH ST. IMPS.: MOTOR CITY WAY TO FOUNTAIN CREEKEngineering
2ACADEMY BLVD. RECONSTRUCTION BIJOU TO AIRPORTConstruction
3ACADEMY BLVD. RECONSTRUCTION FOUNTAIN TO MILTON PROBY PKWY.Construction
4ACADEMY BLVD. OVER COTTONWOOD CREEK BRIDGE REPLACEMENTComplete
5AIRPORT RD. OVER SPRING CREEK BRIDGE REPLACEMENTComplete
6BARNES RD. IMPROVEMENTS, SOLAR RIDGE TO POWERSComplete
7BLACK FOREST RD. IMPROVEMENTS: WOODMEN TO RESEARCHConstruction
8CENTENNIAL BLVD. EXTENSION: FILLMORE TO FONTANEROComplete
9CENTENNIAL BLVD. RECONSTRUCTION GARDEN OF THE GODS TO FILLMOREComplete
10CHESTNUT ST. OVER S. DOUGLAS CREEK BRIDGE REPLACEMENTComplete
11CIRCLE DR. OVER FOUNTAIN CREEK BRIDGE REHABILITATIONConstruction
15DUBLIN RD. IMPROVEMENTS: BRIDLE PASS WAY TO POWERSComplete
16EL PASO BRIDGE OVER FOUNTAIN CREEK TRIBUTARY REPLACEMENTComplete
17ENCHANTED CIRCLE OVER SAND CREEK TRIBUTARY BRIDGE REPLACEMENTComplete
18GALLEY RD. ROAD BRIDGE OVER WEST FORK SAND CREEKConstruction
19I-25 RAMPS: SOUTH NEVADA/ TEJON ST. CORRIDOR IMPROVEMENTSConstruction
20LAS VEGAS ST./ ROYER UPRR CROSSING RELOCATIONEngineering
21OLD RANCH RD. IMPROVEMENTS AND BRIDGE CONSTRUCTIONComplete
22PIKES PEAK AVE.: COLORADO TO PRINTERS PKWY. PAVEMENT RECONSTRUCTIONComplete
23PLATTE AVE. OVER SAND CREEK BRIDGE REPLACEMENTComplete
24PLATTE AVE. CONNECTION TO I-25 STUDYComplete
25PLATTE AVE. CORRIDOR IMP. STUDYComplete
26S. CHEYENNE CANYON RD. 1 OVER CHEYENNE CREEK BRIDGE REPLACEMENTComplete
27SHOOK’S RUN BRIDGE CORRIDOR STUDYComplete
28STAPLETON DR./ BRIARGATE BLVD. CORRIDOR STUDYComplete
29TUTT BLVD EXTENSION: DUBLIN TO TEMPLETON GAP RDConstruction
30UPRR MAINLINE OVER FONTANERO BRIDGE REPLACEMENTEngineering
31UPRR NEVADA & TEJON ST. CROSSING RECONSTRUCTION (DESIGN ONLY)Engineering
32W. COLORADO AVE. RECONSTRUCTION: 31ST ST. TO US 24Complete
33W. FILLMORE OVER UNNAMED CHANNEL BRIDGE REPLACEMENTComplete
34WOODMEN ROAD IMPROVEMENTS: UNION CONTINUOUS FLOW INTERSECTIONComplete