Logo of the Pikes Peak Rural Transportation Authority with the tagline Promises Made, Promises Kept

719-471-7080

City of Colorado Springs 2024 Second Quarter Report – PPRTA III – Dublin Boulevard Improvements – Peterson Road to Marksheffel Road

Construction progress bar showing the current status as 60 percent engineering

Current Phase: Design
Engineering Percent Complete: 45%
Anticipated Construction Date: April 2025

Project Description: This project will make improvements to Dublin Blvd from approximately Peterson Rd to Marksheffel Rd. Improvements include widening the existing roadway from one lane in each direction to two lanes in each direction with a raised median and multi-use shoulders per the City standard section for principal arterial roadways.

Figure 34. Map of project area

Map of the area with Dublin Boulevard from the intersection west of Peterson Road to Marksheffel Road labeled

Figure 35. Dublin Blvd and Peterson Rd. looking West

Street-level photograph of Dublin Boulevard and Peterson Road

Budget

Funding SourceEstimated Project Cost1ObligatedSpent to Date (Actual)Percent Spent to Date2
PPRTA – City Portion$16,600,000$697,633$338,23548%
Total$16,600,000$697,633$338,23548%
  1. Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
  2. Actual funds spent of the current obligated amount.

Highlights:

  • Consultant completed 30% engineering documents and is working toward 60%.
  • Completed SUE and survey to further identify utility conflicts and refine drainage design.
  • Collaborating with Marksheffel Rd CM/CG team to deliver Dublin Blvd as a phase of the Marksheffel project.