Current Phase: Design
Engineering Percent Complete: 45%
Anticipated Construction Date: April 2025
Project Description: This project will make improvements to Dublin Blvd from approximately Peterson Rd to Marksheffel Rd. Improvements include widening the existing roadway from one lane in each direction to two lanes in each direction with a raised median and multi-use shoulders per the City standard section for principal arterial roadways.
Figure 34. Map of project area

Figure 35. Dublin Blvd and Peterson Rd. looking West

Budget
| Funding Source | Estimated Project Cost1 | Obligated | Spent to Date (Actual) | Percent Spent to Date2 |
|---|---|---|---|---|
| PPRTA – City Portion | $16,600,000 | $697,633 | $338,235 | 48% |
| Total | $16,600,000 | $697,633 | $338,235 | 48% |
- Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
- Actual funds spent of the current obligated amount.
Highlights:
- Consultant completed 30% engineering documents and is working toward 60%.
- Completed SUE and survey to further identify utility conflicts and refine drainage design.
- Collaborating with Marksheffel Rd CM/CG team to deliver Dublin Blvd as a phase of the Marksheffel project.