City of Colorado Springs 2024 Second Quarter Report – PPRTA II – Tutt Boulevard Extension – Dublin to Templeton Gap Road

A progress bar showing an arrow halfway through the construction phase

Current Phase: Construction
Construction Percent Complete: 75% (Phase 1 of 2, built); Phase 2 Construction 50%
Construction Start: May 23, 2024

Project Description: The Tutt Boulevard extension is a joint PPRTA Colorado Springs/El Paso County project. Tutt Boulevard will be extended north from Dublin Boulevard and connect with the existing Tutt Boulevard, approximately 1,000 feet north. Phase 1 (from Dublin Boulevard to Vickie Lane) was completed in March 2016. Phase 2 (from Vickie Lane to Spring Breeze Drive) construction started May 23 and is anticipated to take 6-7 months to complete.

Figure 16. Old pavement removal

A photo of old pavement being removed

Figure 27. Sanitary sewer installation

A photo of a sanitary sewer being installed

Budget

Funding SourceEstimated Project Cost1ObligatedSpent to Date (Actual)Percent Spent to Date2
PPRTA$5,279,518$3,662,779$1,770,62348%
Developer Contribution$281,000$281,000$281,000100%
Total$5,560,518$3,943,779$2,051,62352%
  1. Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
  2. Actual funds spent of the current obligated amount.

Highlights:

  • Phase 1 completed in 2016.
  • Phase 2 construction started May 23, 2024.
  • Utility installation and relocations underway.