
Current Phase: Construction
Construction Percent Complete: 75% (Phase 1 of 2, built); Phase 2 Construction 50%
Construction Start: May 23, 2024
Project Description: The Tutt Boulevard extension is a joint PPRTA Colorado Springs/El Paso County project. Tutt Boulevard will be extended north from Dublin Boulevard and connect with the existing Tutt Boulevard, approximately 1,000 feet north. Phase 1 (from Dublin Boulevard to Vickie Lane) was completed in March 2016. Phase 2 (from Vickie Lane to Spring Breeze Drive) construction started May 23 and is anticipated to take 6-7 months to complete.
Figure 16. Old pavement removal

Figure 27. Sanitary sewer installation

Budget
| Funding Source | Estimated Project Cost1 | Obligated | Spent to Date (Actual) | Percent Spent to Date2 |
|---|---|---|---|---|
| PPRTA | $5,279,518 | $3,662,779 | $1,770,623 | 48% |
| Developer Contribution | $281,000 | $281,000 | $281,000 | 100% |
| Total | $5,560,518 | $3,943,779 | $2,051,623 | 52% |
- Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
- Actual funds spent of the current obligated amount.
Highlights:
- Phase 1 completed in 2016.
- Phase 2 construction started May 23, 2024.
- Utility installation and relocations underway.
