Current Phase: Construction
Construction Start Date: April 2022
Anticipated Completion Date: December 2024
Project Description: The project will widen Black Forest Road to a four-lane principal arterial cross-section from Woodmen Road to Research Parkway and include a new bridge over Cottonwood Creek. The existing and proposed development in the City and the County require more capacity on Black Forest Road than the current two-lane section provides.
Figure 10: Northbound prepped for paving

Figure 11: Northbound Black Forest Road after paving

Budget
| Funding Source | Estimated Project Cost1 | Obligated | Spent to Date (Actual) | Percent Spent to Date2 |
|---|---|---|---|---|
| PPRTA | $30,793,970 | $30,482,880 | $24,681,736 | 81% |
| ARPA | $1,900,000 | $1,884,970 | $1,820,583 | 97% |
| CSU | $1,315,569 | $1,252,760 | $1,163,152 | 93% |
| Other Utilities | $62,809 | $- | $- | 0% |
| SWENT | $43,000 | $43,000 | $43,000 | 100% |
| Total | $34,115,348 | $33,663,610 | $27,708,471 | 82% |
- Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
- Actual funds spent of the current obligated amount.
Highlights:
- Roadway paved from Cowpoke Rd to Research Blvd.
- Completed tributary channel improvements.
- Completing Woodmen Rd to Vollmer Rd northbound top paving and striping.
- Grading north of Research Blvd to end of project.