
Current Phase: Construction
Construction Start Date: March 2023
Anticipated Completion Date: September 2025 (2.5-year construction period)
Project Description: Academy Boulevard between Fountain Boulevard and Milton Proby Parkway is a six-lane road with poor pavement and with curb, gutter, and median conditions requiring replacement. The project length of 12,500 feet includes remediation of the pavement area that experiences subsidence due to an abandoned landfill and installation of a new 24” waterline. Poor drainage is contributing to pavement decline, so a new storm water system is being designed to alleviate ponding issues. Planned improvements incorporate recommendations from the Great Streets Corridor Study, including a 10-foot-wide multi-use path.
Figure 8: 8″ waterline

Figure 9: 8″ waterline installation

Budget
| Funding Source | Estimated Project Cost1 | Obligated | Spent to Date (Actual) | Percent Spent to Date2 |
|---|---|---|---|---|
| PPRTA | $49,029,331 | $47,610,352 | $11,944,655 | 25% |
| CSU | $3,982,454 | $3,944,828 | $173,679 | 4% |
| ARPA | $3,500,000 | $3,500,000 | $3,500,000 | 100% |
| Total | $56,511,785 | $55,055,180 | $15,618,333 | 28% |
- Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
- Actual funds spent of the current obligated amount.
Highlights:
- Completed installation of 24” waterline between Drennan and Hancock Expressway.
- Installation of 8” laterals from the mainline.
- Repaving over installed waterline.
