City of Colorado Springs 2024 Second Quarter Report – A-list Capital Programs – Citywide Congestion and Incident Management Signal Improvements Phase I

Implement Citywide/Regional Intelligent Transportation Systems (ITS) to improve traffic operations, coordinate systems, and improve safety. Improvements may include monitoring systems, hardware and software, message systems, metering, communication infrastructure, and specialized equipment and staff.

Program Spend and Completion Status

Program20212022202320241Totals
Traffic ITS Upgrades$497,054$264,563$274,167$19,757$1,055,540
Traffic Signal System Upgrades$364,221$100,142$122,896$80,048$667,307
Software$25,000$81,105$85,591–$191,696
Total Spend/Encumbered$886,275$445,810$482,653$99,804$1,914,542
Budget   $1,258,645 
% Spent/Encumbered215%32%38%8% 
Percent of Program
% of Traffic ITS Equipment56%59%57%20%55%
% of Traffic Signal Equipment41%22%25%80%35%
% of Software3%18%18%0%10%
  1. 2024 Budget includes $412,000 budget allocation and $846,645 2023 carryover.

Projects Completed in Q2 2024 and Continuing Efforts

  • Purchase of traffic signal controllers.
  • Purchase school zone clocks and timers.