This program constructs drainage improvements needed in advance of roadway rehabilitation or reconstruction efforts.
Program Spend and Completion Status
| Program | 2021 | 2022 | 2023 | 20241 | Totals |
|---|---|---|---|---|---|
| Drainage Improvements | $412,000 | $412,000 | $412,000 | $412,000 | $1,648,000 |
| Total Spent/Encumbered | $412,000 | $412,000 | $412,000 | $412,000 | $1,648,000 |
| Budget | $412,000 | ||||
| % Spent/Encumbered | 100% | 100% | 100% | 100% | |
| Percent of Program | |||||
| Drainage Improvements % of Program | 100% | 100% | 100% | 100% | 100% |
- 2024 Budget $412,000.
Narrative
The following locations will have updated storm pipe lining:
- Broadmoor Hills Drive
- Custer Avenue
- Deliverance Drive
- N Hancock Avenue
- Palmer Park Boulevard
- East Platte Avenue
- Templeton Gap Road
- Vickers Drive