City of Colorado Springs 2024 Second Quarter Report – A-list Capital Programs – Citywide Roadway Safety and Traffic Operations Phase I

This capital program includes intersection and corridor “spot” improvements to mitigate existing safety and traffic flow deficiencies. Proposed projects of this type will include the construction of traffic signals, roundabouts, auxiliary traffic lanes, traffic calming features, and other lower-cost geometric improvements. These projects may also install infrastructure such as guard rail, construct/reconstruct medians at intersections to improve capacity, and install traffic control devices as warranted to improve traffic operations and safety.

Program Spend and Completion Status

Program20212022202320241Totals
Intersection Improvements$805,103$656,928$941,542$4,854,881$7,258,454
Safety Projects$139,011$454,229$693,152$120,304$1,406,696
Transportation Studies$263,083$147,512$347,383$51,897$809,875
Sierra / Vermijo$957,760$957,760
Total Spend$2,164,957$1,258,669$1,982,077$5,027,082$10,432,785
Budget   $20,775,959 
% Spent/Encumbered111%32%17%24% 
Percent of Program
% of Intersection Improvements37%52%48%97%70%
% of Safety Projects6%36%35%2%13%
% of Transportation Studies12%12%18%1%8%
% of Sierra / Vermijo44%0%0%0%9%
  1. 2024 Budget includes $1,000,000 budget allocation, $9,775,959 2023 carryover, and $10,000,000 line transfer allocation for Marksheffel.

Projects Completed in Q2 2024 and Continuing Efforts

  • Cheyenne Blvd/Cheyenne Road design efforts.
  • Marksheffel Road construction.