City of Colorado Springs 2024 Second Quarter Report – A-list Capital Programs – Citywide On-street Bikeway Improvements Phase I

The City’s Comprehensive Plan, Intermodal Transportation Plan (ITP), and the Complete Streets ordinance strongly recommend streets be designed to accommodate safe and efficient bicycle travel/access. There are many locations in the city where safe and adequate bicycle travel and access are not provided or need enhancement. Proposed bikeway improvements will continue to improve and construct bike lanes in accordance with the ITP and the City’s Bicycle Plan, install bicycle lanes (where feasible) to close gaps on the existing on-street bike lane network, improve connections from on-street bike lanes to the Colorado Springs trail system and residential/commercial centers, and develop/implement improved signage to provide better wayfinding for bicyclists.

Program Spend and Completion Status

Program20212022202320241Totals
On-Street Bike Facilities$218,045$18,772$84,510$23,769$345,096
Trail Crossings$367,984$81,131$381,236$-$830,351
Total Spend$586,029$99,903$465,746$23,769$1,175,447
Budget   $1,477,854 
% Spent142%8%30%2% 
Percent of Program
% of On-Street Bike Facilities37%19%18%100%29%
% of Trail Crossings63%81%82%0%71%
  1. 2024 Budget includes $412,000 budget allocation and $1,065,854 2023 carryover.

Projects Completed in Q2 2024 and Continuing Efforts

  • Tejon Street Revitalization multi-modal design.
  • Pikes Peak and Cucharras bike boulevard alternative development and design.