Citizen Advisory Committee – September 4, 2024: Quarterly Reports From Member Governments – City of Colorado Springs 2024 Second Quarter Report – PPRTA II – Circle Drive Bridges Over Hancock and Fountain Creek Rehabilitation

A project status bar indicating an arrow one-quarter through the construction phase

Current Phase: Construction
Construction Percent Complete: 30%
Anticipated Completion Date: Late 2025/Early 2026

Project Description: Constructed by the Colorado Department of Highways in 1963, the Circle Drive Bridges carry eastbound and westbound lanes of Circle Drive on separate structures. The western pair of bridges cross Fountain Creek. The eastern pair of bridges cross the BNSF Railroad, a Fountain Mutual Irrigation Company conveyance facility, the Hancock Expressway, and East Las Vegas Street. This project will replace the deteriorating structures with four new bridges. The new bridges will have wider cross sections to allow for better pedestrian movement.

Figure 12: Construction over the eastbound Circle Bridge

Aerial photo of bridge construction

Figure 13: Construction of the prefabricated concrete bridge girders

Photo of construction workers with prefabricated concrete bridge girders

Budget

Funding SourceEstimated Project Cost1ObligatedSpent to Date (Actual)Percent Spent to Date2
PPRTA$45,204,000$43,770,739$15,197,90435%
CSU$3,420,747$3,420,747$745,92022%
PPRTA Traffic$913,852$913,852$-0%
Total$49,538,599$48,105,338$15,943,82433%
  1. Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
  2. Actual funds spent of the current obligated amount.

Highlights:

  • Soil nail wall construction is ongoing for the new eastbound bridge.
  • Pier construction is almost complete for the new eastbound bridge.
  • Northeast bound bridge girder fabrication completed. Girder placements anticipated in Q3 2024.