Citizen Advisory Committee – September 4, 2024: Quarterly Reports From Member Governments – El Paso County 2024 Second Quarter Report – Capital Program PPRTA Project Summary

The following table summarizes the current project Status.

Project NameProject Status
Beacon Lite RoadDesign Complete; Finalizing Property Acquisition — 95%
Black Forest Road (Joint w/ City
of Colorado Springs)
City-led Project
Deer Creek, Base Camp, Microscope Way (aka Emigrant)Design — near 100% with original scope and added RAB
Eastonville RoadDesign — Phase I near 100%
Phase II — 25%
Fontaine Blvd/Security Blvd/Widefield Blvd IntersectionConstruction 85%
Highway 105 Project A — Interstate 25 to Lake Woodmoor DrConstruction – 50%
Highway 105 Project B — Lake Woodmoor to MartingaleDesign — 90%
Highway 105 Project C-E — Martingale to SH83Design — 25%
Main St/Security BlvdConstruction — 100% (Substantial Completion)
Mesa Ridge ParkwayFinal Design & Prop. Acq.
Monument Hill RoadComplete
New Meridian/US 24 Int.Complete
South Academy BlvdConstruction – 40%
Stapleton Drive/Briargate Blvd
Corridor Study (joint w/ City of Colorado Springs)
Complete
Tutt Blvd Extension (Joint w/City of Colorado Springs)City-led Project
West Colorado Avenue (joint w/ City of Manitou Springs/City of Colorado Springs)Closeout