The following table summarizes the current project Status.
| Project Name | Project Status |
|---|---|
| Beacon Lite Road | Design Complete; Finalizing Property Acquisition — 95% |
| Black Forest Road (Joint w/ City of Colorado Springs) | City-led Project |
| Deer Creek, Base Camp, Microscope Way (aka Emigrant) | Design — near 100% with original scope and added RAB |
| Eastonville Road | Design — Phase I near 100% Phase II — 25% |
| Fontaine Blvd/Security Blvd/Widefield Blvd Intersection | Construction 85% |
| Highway 105 Project A — Interstate 25 to Lake Woodmoor Dr | Construction – 50% |
| Highway 105 Project B — Lake Woodmoor to Martingale | Design — 90% |
| Highway 105 Project C-E — Martingale to SH83 | Design — 25% |
| Main St/Security Blvd | Construction — 100% (Substantial Completion) |
| Mesa Ridge Parkway | Final Design & Prop. Acq. |
| Monument Hill Road | Complete |
| New Meridian/US 24 Int. | Complete |
| South Academy Blvd | Construction – 40% |
| Stapleton Drive/Briargate Blvd Corridor Study (joint w/ City of Colorado Springs) | Complete |
| Tutt Blvd Extension (Joint w/City of Colorado Springs) | City-led Project |
| West Colorado Avenue (joint w/ City of Manitou Springs/City of Colorado Springs) | Closeout |