Citizen Advisory Committee – September 4, 2024: Quarterly Reports From Member Governments – City of Colorado Springs 2024 Second Quarter Report – PPRTA II – South Cheyenne Canyon Road 1 Over Cheyenne Creek Bridge Replacement

A project status bar indicating a complete project

Current Phase: Complete
Percent Complete: 100%
Construction Finish: June 2024

Project Description: Believed to be built in 1957, the South Cheyenne Canon Road Bridge is a multi-type structure located just north of the Seven Falls entrance. The bridge is load-posted and has reached the end of its service life, requiring replacement. The project will provide a new roadway bridge and a pedestrian/trail bridge for better flow and safety. The new roadway structure will be 150’ east of the existing structure and the pedestrian bridge will align with the Chamberlain Trail system.

Figure 24. S. Cheyenne Canyon Bridge looking West

South Cheyenne Canyon Bridge looking west

Figure 25. S. Cheyenne Canyon Pedestrian Bridge

South Cheyenne Canyon Pedestrian Bridge

Budget

Funding SourceEstimated Project Cost1ObligatedSpent to Date (Actual)Percent Spent to Date2
PPRTA$3,467,898$3,418,642.53$2,991,054.3187%
TOPS$117,088$117,088.00$117,088.00100%
Total$3,584,986$3,535,730.53$3,108,142.3188%
  1. Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
  2. Actual funds spent of the current obligated amount.

Highlights:

  • The project began in January 2024 and opened to the roadway to traffic for Memorial Day 2024.
  • Final project completion occurred in June and has received praise from users and tourists.
  • The project provides an improved intersection, pedestrian bridge, and creek side rip rap access for pedestrians and bikes on the Chamberlain Trail.