Citizen Advisory Committee – September 4, 2024: Quarterly Reports From Member Governments – City of Colorado Springs 2024 Second Quarter Report – PPRTA II – El Paso Bridge Over Fountain Creek Tributary Replacement

A project status bar indicating a complete project

Current Phase: Complete
Construction Percent Complete: 100%
Completion Date: Spring 2024

Project Description: Replace an aging bridge structure crossing over a tributary to Fountain Creek commonly known as the Columbia Road Tributary. Recent bridge inspections have determined the structure to be “functionally obsolete” and qualify the bridge for replacement. The bridge is located on El Paso Blvd, approximately 800’ north of W Colorado Ave and 200’ west of S Columbia Road. The structure is approximately 500’ east of the Manitou Springs city limit.

Figure 14: An image of the project area before construction in 2020

El Paso Bridge over Fountain Creek tributary before construction

Figure 15: An image of the project area after construction. Notable additions to the area include bridge rail, guardrail, curb and gutter, sidewalk, and an asphalt surface that replaced many years of utility patching.

A completed El Paso bridge over Fountain Creek tributary

Budget

Funding SourceEstimated Project Cost1ObligatedSpent to Date (Actual)Percent Spent to Date2
PPRTA$1,497,600$1,304,485$1,223,74894%
Total$1,497,600$1,304,485$1,223,74894%
  1. Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
  2. Actual funds spent of the current obligated amount.

Highlights:

  • Paved and striped the road in coordination with the City of Manitou Springs.
  • Removed the detour and opened the road to traffic.
  • Performed punch list walk-throughs with multiple stakeholders.