Citizen Advisory Committee – September 4, 2024: Quarterly Reports From Member Governments – City of Colorado Springs 2024 Second Quarter Report – Maintenance Programs – Roadway Maintenance, Roadway Drainage Pipe, Guardrail, and Concrete Repair Programs

The City has maintenance programs to preserve the service life of infrastructure assets. The largest program is the Roadway Maintenance, Roadway Drainage Pipe, Guardrail, and Concrete Repair Program. Other maintenance programs include Citywide Traffic Signal System Maintenance, Bridge Maintenance, and Capital Project Maintenance.

The road maintenance costs per major work items are summarized below. For each work item, the total expenditure for the past three years and through the second quarter of 2024 is provided. A drawdown chart is also presented for these road maintenance activities. The chart shows the annual allocation in blue, along with the actual and projected monthly expenditures in red, and cumulative balance for the program in green. As the year progresses, the program balance decreases as activities are completed, representing the drawdown. The program plans work and associated expenditures annually to maximize use of available funds.

Detailed reports of asset and material quantities are also provided. Appendix B contains the completed on-call ADA replacement items and a summary of contracts active in the second quarter of 2024.

Costs per major work items for the Citywide Traffic Signal System Maintenance, Bridge Maintenance, and Capital Project Maintenance programs are also summarized.

Material Placed in 2024 for Roadway and Sidewalk Maintenance

The space shuttle landing

Crack Seal –2.5 times as heavy as the Space Shuttle, or 418,025 pounds

Birds eye view of three tennis courts

Sidewalk – 30 Tennis Court, or 76,645 square feet.

Pikes Peak in the morning with fog in the foreground

Curb and Gutter – 1.2 times the height of Pikes Peak, or 16,846 linear feet

Program Spend and Completion Status

Program20212022202320241Totals
Chipseal$1,536,037$1,655,736$1,478,418$-$4,670,191
Crackseal$1,384,807$2,155,236$1,443,562$863,390$5,846,995
Digout/Patching$2,384,430$719,884$534,522$354,899$3,993,735
Slurry Seal$-$-$1,310,984$698,366$2,009,350
Overlay$885,130$3,752,784$-$-$4,637,914
Pavement Assessment$48,234$-$-$-$48,234
Pre-overlay Pipe$1,758,8511,368,240$1,549,926$80,901$4,757,918
Guardrail$124,797$123,701$100,738$146,451$495,687
Pre-overlay Concrete$-$-$-$-$-
ADA/On-call$9,421,215$11,000,034$9,236,531$3,433,651$33,091,431
Independent ADA Ramp Assessment$45,105$41,592$44,241$33,449$164,387
Cost Share Program$76,855$128,446$88,444$28,955$322,701
Sidewalk Vertical Displacement Mitigation Program$174,140$174,977$188,344$175,000$712,461
Truncated Domes Program$144,976$150,000$56,522$-$451,498
Program Support$1,088,823$1,133,875$659,615$317,230$3,199,542
Other$14,457$639,864$4,433,209$1,880,760$6,968,291
In-House Maintenance Program$5,287,555$4,918,770$5,142,038$1,571,264$16,919,628
Total Spend/Encumbered$24,375,412$27,963,139$26,367,096$9,584,317$88,289,964
Budget$27,291,453
% Spent/Encumbered72%80%106%35% 
Percent of Program
Chipseal % of Program6%6%6%0%5%
Crackseal % of Program6%8%5%3%7%
Digout/Patching % of Program10%3%2%1%5%
Slurry Seal0%0%5%3%2%
Overlay % of Program4%13%0%0%5%
Pavement Assessment % of Program0%0%0%0%0%
Pre-overlay Pipe % of Program7%5%6%0%5%
Guardrail % of Program1%0%0%1%1%
Pre-overlay Concrete % of Program0%0%0%0%0%
ADA/On-call % of Program39%39%35%13%37%
Independent ADA Ramp Assessment % of Program0%0%0%0%0%
Cost Share Program % of Program0%0%0%0%0%
Sidewalk Vertical Displacement Mitigation % of Program1%1%1%1%1%
Truncated Domes Program % of Program1%1%1%0%1%
Program Support % of Program4%4%3%1%4%
Other % of Program0%2%17%7%8%
In-House Maintenance Program % of Program22%18%20%6%19%
  1. 2024 Budget includes $22,159,895 budget allocation, $5,131,558 from 1st 2024 budget amendment.

Projects Completed in Q2 2024 and Continuing Efforts

Other Line Item Breakdown:

  • Right of Way (ROW) structure improvements Rustic Hills Phase 2 Project
  • In-House program supports:
  • Potholes Minor Paving
  • In-house crackseal program In-House concrete work

Upcoming projects/activities:

  • Structures in the right-of-way is in progress. Rustic Hills – Phase 2 is in progress.

Drawdown

The chart shows the annual allocation in blue, the actual and projected monthly expenditures in red, and the cumulative balance for the program in white. As the year progresses, the program balance decreases as activities are completed, representing the drawdown. The program plans work and associated expenditures annually to maximize use of available funds; however, a small percentage of the annual allocation is typically carried into the next year and is applied to ongoing maintenance activities.

Bar chart showing the Colorado Springs drawdown of PPRTA funds from January 2020 through June 2024

Amounts in the drawdown are estimates rounded to the nearest $10,00.

MonthAllocationExpendituresCumulative Balance
January 2020$18,830,000$23,770,000
February 2020$590,000$23,100,000
March 2020$930,000$22,010,000
April 2020$1,850,000$20,080,000
May 2020$1,510,000$18,330,000
June 2020$510,000$17,830,000
July 2020$2,600,000$14,980,000
August 2020$2,430,000$14,810,000
September 2020$1,260,000$13,310,000
October 2020$3,100,000$10,050,000
November 2020$1,100,000$8,790,000
December 2020$4,860,000$3,690,000
January 2021$18,750,000$22,680,000
February 2021$590,000$21,930,000
March 2021$760,000$21,000,000
April 2021$1,260,000$19,580,000
May 2021$2,100,000$17,240,000
June 2021$3,690,000$1,680,000$19,160,000
July 2021$1,430,000$17,770,000
August 2021$1,180,000$16,240,000
September 2021$4,190,000$1,680,000$18,750,000
October 2021$4,610,000$13,980,000
November 2021$2,430,000$11,470,000
December 2021$2,850,000$8,460,000
January 2022$23,010,000$1,760,000$29,790,000
February 2022$1,100,000$28,530,000
March 2022$590,000$27,780,000
April 2022$1,680,000$25,860,000
May 2022$2,350,000$23,260,000
June 2022$3,100,000$23,120,000
July 2022$1,760,000$21,090,000
August 2022($1,250,000)$510,000$19,160,000
September 2022$4,690,000$14,400,000
October 2022$2,520,000$11,720,000
November 2022$2,850,000$8,710,000
December 2022$3,020,000$5,610,000
January 2023$23,010,000$1,930,000$26,530,000
February 2023$340,000$26,190,000
March 2023$930,000$25,190,000
April 2023$1,350,000$23,600,000
May 2023$1,430,000$22,010,000
June 2023$3,100,000$18,970,000
July 2023$2,020,000$18,500,000
August 2023$3,270,000$15,070,000
September 2023$2,020,000$12,890,000
October 2023$3,770,000$8,960,000
November 2023$4,020,000$4,780,000
December 2023$2,270,000$2,270,000
January 2024$22,010,000$430,000$23,850,000
February 2024$840,000$22,850,000
March 2024$590,000$22,090,000
April 2024$2,020,000$20,000,000
May 2024$1,930,000$17,910,000
June 2024$1,350,000$16,420,000
Program201920202021202220232024Totals
Slurry Seal
Area Covered (Square Yards)––––399,221203,013602,234
Lane Miles Improved––––623193
Asphalt 
Tons Placed13,31713,288–18,879– 45,484
Lane Miles Improved–––18– 18
Chip Seal 
Area Covered (Square Yards)–745,557458,865418,414351,708–1,974,545
Lane Miles Improved–115716555–306
Crack Seal 
Material Placed (Pounds)–995,050934,7851,343,969719,707418,0254,411,536
Digout and Wide Crack Mitigation 
Tons Placed–1,8555,8912,0091,20876011,722
On Call and ADA 
Curb and Gutter (Linear feet)22,15736,95560,03667,09552,87316,777255,892
Installed Sidewalk (Square feet)87,362178,660273,328290,584186,31376,4141,092,660
New Pedestrian Ramps (Each)14522326512519102879
Retrofitted Pedestrian Ramps (Each)1861721661264340733
Cross pans (Each)405485611028278
Cost Share Program 
Curb and Gutter (Linear feet)1,5961,07492788822694,576
Installed Sidewalk (Square feet)6,70211,2557,3099,7868342,23138,117
Sidewalk Vertical Displacement Mitigation Program 
Number of Cuts2,1543,3453,5892,9862,0222,03216,128
Pre-Overlay Pipe 
Pipe Lines (Linear Feet)–5844,1079643,238–8,893
Guardrail 
Projects Completed19151813151292