Citizen Advisory Committee – September 4, 2024: 2024 Capital, Maintenance and Public Transportation Contracts: City of Colorado Springs – Legacy Loop: Monument Creek Stabilization Project: Park Trail Contribution (Pikes Peak Greenway)

To:

  • Pikes Peak Rural Transportation Authority (PPRTA) Board of Directors
  • Pikes Peak Rural Transportation Authority Citizen Advisory Committee (CAC)

From: City of Colorado Springs – Emily Duncan, Trails Development Coordinator

CC: City of Colorado Springs – Gayle Sturdivant, PE, PMP, City Engineer/ Deputy Public Works Director

Date: September 4, 2024


CONTRACT

Project: Monument Creek Stabilization Project: Park Trail Contribution (Pikes Peak Greenway)

Contract Amount: PPRTA: $500,000.00, Other: $0.00

Type: (Choose all that apply)

  • ☒ Capital
  • ☐ Maintenance
  • ☐ Transit
  • ☐ Consultant
  • ☐ Equipment
  • ☐ Construction
  • ☐ Materials
  • ☐ Personnel
  • ☐ Other (description)

Project Description: This request is for $500,000 to cover the trail amenities provided in Colorado Springs Utilities’ Monument Creek Stabilization project. This project largely addressed wastewater infrastructure within the creek that was at risk for potential erosion and damage. With this, Utilities provided ramp access to the creek, also providing a recreational amenity, and a trail underpass at Mesa Road for the Pikes Peak Greenway. Trail and trail-related construction far exceeds the $500,000 one-time contribution by PRCS, although an Executive Agreement established that PRCS would contribute to the north ramp for the trail underpass to establish full connectivity for the Pikes Peak Greenway.

VENDOR INFORMATION

Vendor: Colorado Springs Utilities
Contract No.: N/A (Invoice)
Contract Term (start/end dates) / Duration: Work Completed

FINANCIAL INFORMATION

Budget CategoryProject CategoryTask Order AmountFunds Available2024 Budget AmountBudget Code
Legacy Loop: West Pikes Peak Greenway☒ Capital
☐ Maintenance
☐ Transit
$500,000$1,983,308$1,983,30803-20-5030038

Comments: One-time project contribution per Executive Agreement with CSU.  

AWARD PROCESS

  • ☐ IFB (Invitation for Bid)
  • ☐ RFP (Request for Proposal)
  • ☐ Sole Source
  • ☒ Other

Comments: Executive agreement executed in October 2023 for a contribution from PRCS to Utilities for trail amenities associated with project, not to exceed $500,000.

Attachments:

  • ☐ Location Map
  • ☐ Award Process Document
  • ☐ Final Design Scope and Fee

Location Map

A map showing the Pikes Peak Greenway indicated on each side of Monument Creek near Mesa Road

Image title

Site map with the Pikes Peak Greenway highlighted on each side of Monument Creek at Mesa Road.

Alternative text for image

A map showing the Pikes Peak Greenway indicated on each side of Monument Creek near Mesa Road