Citizen Advisory Committee – October 2, 2024: Staff Field Review Report, El Paso County Program Status Reports

Program Status Reports: 2024 Maintenance Programs Second Quarter

2024 Gravel Program

El Paso County crews completed 33.54 Lane Miles of gravel on Richardson Road, Sand Place, Angus Court, Canter Road, Charter Oak Ranch Road, Smith Road, Big Springs Road, Handle Road, Gull Lane, Horseback Trail, Heritage Park Trail, Partridge Lane, Tahosa Lane, Ridgeway Lane, Leather Chaps Drive, Lariat Lane, Crooked Spur Lane, Curb Bit Lane, Spanish Bit Drive, Struthers Loop and Baggett Road in the Second Quarter.

Scanned image of a photograph of a grader working gravel on a road
Scanned image of a photograph of a construction crews working gravel on a road

2024 Chip Seal Program

El Paso County crews completed 23.6 Lane Miles of chip seal on Hay Creek Road, Mission Hill Way, Hodgen Road, Walker Road, Herring Road, and Shoup Road in the Second Quarter.

Scanned image of a photograph of a construction crews applying chip seal on a road
Scanned image of a photograph of a construction crews applying chip seal on a road

2024 Concrete Improvements Program

During the 2nd quarter of 2024, work commenced on the 2023 Concrete Drainage Program. A total of 17 square yards of sidewalk, as well as two drainage improvement projects at Pebble Beach and Palmer Park were completed. HCD has completed a total of $3,908,732.67 of concrete and drainage improvements for the 2023 program totaling $293,220.08 in the 2nd quarter of 2024 and completing the 2023 PPRTA Concrete drainage project.

Palmer Park Drainage Improvement
Pebble Beach Drainage improvement.
97 Suzanne Cir

Scanned image of a photograph showing new concrete for a driveway

Pebble Beach

Scanned image of a photograph of a new culvert

Palmer Park

2024 Asphalt Pavement Program PPRTA

The 2024 PPRTA Asphalt Pavement Program paved 42.92 lane miles in the second quarter of 2024.

Project LocationRehabilitation
Grassland Road (Peaceful Valley Road to Raintree Drive)3″ Overlay
Peaceful Valley Road (Fountain CL to Raintree Drive)3″ Overlay
Raintree Drive (Green Springs to Peaceful Valley Road)Full Depth Reclamation – 3″ OL
Chromium Dive (Park Vista Blvd to Sapphire Drive)2″ Overlay
Queensmere Drive (Scottswood Drive to Roller Coaster Road)Full Depth Reclamation – 3″ OL
Hathaway Drive (US HWY 24 to Galley Road)2″ Full Width Mill – 2″ OL
Pawnee Road (HWY 115 to Commanche Road)3″ Overlay
Calle Corvo (End to Roca Roja Circle)2″ Overlay
Piney Ridge Way (Pagentry Place to Long Timber Lane)Full Depth Reclamation – 3″ OL
Sixpenny Lane (Kings Deer Point to End)Full Depth Reclamation – 3″ OL
Royal Troon Drive (Kings Deer Point to County Line Road) Indi Drive (County Line Road to Aries Drive)Full Depth Reclamation – 3″ OL
Indi Drive (County Line Road to Aries Drive)3″ Overlay
Luther Road (Huber Road to end)3″ Overlay
Grist Mill Way (New London Road to End)3″ Overlay
Ore Cart Way (Fairplay Drive to End)3″ Overlay
Shadowood Drive (White Fawn Drive to Woodmoor Drive)Full Depth Reclamation – 3″ OL
Bradshaw Road (HWY 24 to Murphy Road)3″ Overlay
Draco Circle (Capella Drive to Draco Drive)3″ Overlay
Capella Drive (Draco Circle to Indi Drive)3″ Overlay
Draco Drive (Draco Circle to Indi Drive)3″ Overlay
Blaney Road (Blaney Road to Falcon Highway)3″ Overlay
Elbert Road (Hwy 24 to Judge Orr Road)3″ Overlay

Major Quantities for the 2024 PPRTA Second Quarter:

  • Full Depth Reclamation: 16, 191 square yards
  • Asphalt Paving: 34,375 tons
  • Shouldering: 3,902 tons
  • Striping: 103 gallons
  • Lane Miles Paved: 42.92 miles
  • Milling: 53,763 square yards
  • Tack Oil: 24,734 gallons
  • Asphalt Patching: 0 tons
  • Thermoplastic Marking: 0 square feet
Scanned image of a photograph showing Raintree Drive before resurfacing

Raintree Drive (Before)

Scanned image of a photograph showing Raintree Drive after resurfacing

Raintree Drive (After)

Scanned image of a photograph showing Ore Cart Way before resurfacing

Ore Cart Way (Before)

Scanned image of a photograph showing Ore Cart Way after resurfacing

Raintree Drive (After)