Citizen Advisory Committee – October 2, 2024: IGA Between the PPRTA and CDOT and PPRTA and the City of Colorado Springs for Capital Project Grant, Draft CDOT-PPRTA IGA – Exhibit E: Local Agency Administration Checklist

Colorado Department of Transportation – Local Agency Contract Administration Checklist

Project No.: MTF M240-208

STIP No.: SR27016.017

Project Code: 25190

Region: 02

Project Location: Colorado Springs. Sinton Trail intersecting Centennial Blvd.

Date: 04/16/2024

Project Description: Design and construct Sinton Trail crossing under Centennial Blvd to improve safety and connectivity.

Local Agency: Pikes Peak Rural Transportation Authority, for the benefit of the City of Colorado Springs

Local Agency Project Manager: Ryan Hershberger

CDOT Resident Engineer: Lachelle Davis

CDOT Project Manager: Junior Rodriguez

INSTRUCTIONS
This checklist shall be utilized to establish the contract administration responsibilities of the individual parties to this agreement. The checklist becomes an attachment to the Local Agency agreement. Section numbers (NO.) correspond to the applicable chapters of the CDOT Local Agency Desk Reference. LAWR numbers correspond to the applicable flowchart in the Local Agency Web Resource.

The checklist shall be prepared by placing an “X” under the responsible party, opposite each of the tasks. The “X” denotes the party responsible for initiating and executing the task. Only one responsible party should be selected. When neither CDOT nor the Local Agency is responsible for a task, not applicable (NA) shall be noted. In addition, a “#” will denote that CDOT must concur or approve.

Tasks that will be performed by Headquarters staff will be indicated. The Regions, in accordance with established policies and procedures, will determine who will perform all other tasks that are the responsibility of CDOT.

The checklist shall be prepared by the CDOT Resident Engineer or the CDOT Project Manager, in cooperation with the Local Agency Project Manager, and submitted to the Region Program Engineer. If contract administration responsibilities change, the CDOT Resident Engineer, in cooperation with the Local Agency Project Manager, will prepare and distribute a revised checklist.

Note: Failure to comply with applicable Federal and State requirements may result in the loss of Federal or State participation in funding.

Local Agency WRNumberDescription of TaskResponsible Party
Local AgencyColorado Department of Transportation
Transportation Improvement Program / Statewide Transportation Improvement Program and Long-Range Plans
2.1Review Project to ensure it is consistent with STIP and amendments theretoX
Federal Funding Obligation and Authorization
4.1Authorize funding by phases (CDOT Form 418 – Federal-aid Program Data. Requires FHWA concurrence/involvement)X
Project Development
15.1Prepare Design Data – CDOT Form 463XX
5.2Prepare Local Agency/CDOT Inter-Governmental Agreement (see also Chapter 3)X
25.3Conduct Consultant Selection/Execute Consultant Agreement Project DevelopmentConstruction Contract Administration (including Fabrication Inspection Services)X
3, 3A5.4Conduct Design Scoping Review MeetingX
3,65.5Conduct Public InvolvementX
35.6Conduct Field Inspection Review (FIR)X 
45.7Conduct Environmental Processes (may require FHWA concurrence/involvement)X 
55.8Acquire Right-of-Way (may require FHWA concurrence/involvement)X 
35.9Obtain Utility and Railroad AgreementsX 
35.10Conduct Final Office Review (FOR)X 
3A5.11Justify Force Account Work by the Local AgencyX 
3B5.12Justify Proprietary, Sole Source, or Local Agency Furnished ItemsX 
35.13Document Design Exceptions – CDOT Form 464X 
35.14Prepare Plans, Specifications, Construction Cost Estimates and SubmittalsX 
 5.15Ensure Authorization of Funds for Construction X
 Project Development Civil Rights and Labor Compliance
36.1Set Disadvantaged Business Enterprise (DBE) Goals for Consultant and Construction Contracts (CDOT Region EEO/Civil Rights Specialist). X
 6.2Determine Applicability of Davis-Bacon Act   This project ☐ is X is not exempt   from Davis-Bacon requirements as determined by the functional classification of the project location (Projects located on local roads and rural minor collectors may be exempt.)   CDOT Resident Engineer: Lachelle Davis (Signature on File) Date: 12/21/2022 X
 6.3Set On-the-Job Training Goals (CDOT Region EEO/Civil Rights Specialist) X
36.4Title VI AssurancesX 
6,7 Ensure the correct Federal Wage Decision, all required Disadvantaged Business Enterprise/On-the-Job Training special provisions and FHWA Form 1273 are included in the Contract (CDOT Resident Engineer) X
 Advertise, Bid and Award of Construction Projects
6,77.1Obtain Approval for Advertisement Period of Less Than Three WeeksX 
77.2Advertise for BidsX 
77.3Distribute “Advertisement Set” of Plans and SpecificationsX 
77.4Review Worksite and Plan Details with Prospective Bidders While Project Is Under AdvertisementX 
77.5Open BidsX 
77.6Process Bids for Compliance  
  Check CDOT Form 1415 – Commitment Confirmation when the low bidder meets DBE goals X
  Evaluate CDOT Form 1416 – Good Faith Effort Report and determine if the Contractor has made a good faith effort when the low bidder does not meet DBE goals X
  Submit required documentation for CDOT award concurrenceX 
 7.7Concurrence from CDOT to Award X
 7.8Approve Rejection of Low Bidder X
7,87.9Award Contract X
87.10Provide “Award” and “Record” Sets of Plans and SpecificationsX 
 Construction Management
88.1Issue Notice to Proceed to the ContractorX 
88.2Project SafetyX 
8.8.3Conduct Conferences  
  Pre-Construction Conference (Appendix B) Fabrication Inspection NotificationsX 
  Pre-survey Construction stakingMonumentationX 
  Partnering (Optional)X 
  Structural Concrete Pre-Pour (Agenda is in CDOT Construction Manual)X 
  Concrete Pavement Pre-Paving (Agenda is in CDOT Construction Manual)X 
  HMA Pre-Paving (Agenda is in CDOT Construction Manual)X 
88.4Develop and distribute Public Notice of Planned Construction to media and local residentsX 
98.5Supervise Construction  
  A Professional Engineer (PE) registered in Colorado, who will be “in responsible charge of construction supervision.” Local Agency Professional Engineer: Kevin Diekelman Phone Number: 719-385-5479X 
  Provide competent, experienced staff who will ensure the Contract work is  constructed in accordance with the plans and specificationsX 
  Construction inspection and documentationX 
  Fabrication Inspection and documentationX 
98.6Approve Shop DrawingsX 
98.7Perform Traffic Control InspectionsX 
98.8Perform Construction SurveyingX 
98.9Monument Right-of-WayX 
9,9A8.10Prepare and Approve Interim and Final Contractor Pay Estimates. Collect and review CDOT Form 1418 (or equivalent) Provide the name and phone number of the person authorized for this task. Local Agency Representative: Ryan Hershberger Phone Number: 719-385-5407X 
98.11Prepare and Approve Interim and Final Utility and Railroad BillingsX 
9B8.12Prepare and Authorize Change OrdersX 
9B8.13Submit Change Order Package to CDOTX 
9A8.14Prepare Local Agency Reimbursement RequestsX 
98.15Monitor Project Financial StatusX 
98.16Prepare and Submit Monthly Progress ReportsX 
98.17Resolve Contractor Claims and DisputesX 
 8.18Conduct Routine and Random Project Reviews Provide the name and phone number of the person responsible for this task. CDOT Resident Engineer: Lachelle Davis Phone Number: 719-562-5516 X
98.19Ongoing Oversight of DBE ParticipationX 
 Materials
9,9C9.1Discuss Materials at Pre-Construction Meeting Buy America documentation required prior to installation of steelX 
9,9C9.2Complete CDOT Form 250 – Materials Documentation Record Generate form, which includes determining the minimum number of required tests and applicable material submittals for all materials placed on the projectUpdate the form as work progressesComplete and distribute form after work is completedXX
9C9.3Perform Project Acceptance Samples and TestsX 
9C9.4Perform Laboratory Verification TestsX 
9C9.5Accept Manufactured Products   Inspection of structural components: Fabrication of structural steel and pre-stressed concrete structural componentsBridge modular expansion devices (0” to 6” or greater)Fabrication of bearing devicesX 
9C9.6Approve Sources of MaterialsX 
9C9.7Independent Assurance Testing (IAT), Local Agency Procedures X CDOT Procedures Generate IAT scheduleSchedule and provide notificationConduct IATX 
9C9.8Approve mix designs ConcreteHot mix asphaltX 
9C9.9Check Final Materials DocumentationX 
9C9.10Complete and Distribute Final Materials DocumentationXX
 Construction Civil Rights and Labor Compliance
910.1Fulfill Project Bulletin Board and Pre-Construction Packet RequirementsX 
8,910.2Process CDOT Form 205 – Sublet Permit Application Review and sign completed CDOT Form 205 for each subcontractor, and submit to EEO/Civil Rights SpecialistX 
910.3Conduct Equal Employment Opportunity and Labor Compliance Verification Employee Interviews. Complete CDOT Form 280X 
910.4Monitor Disadvantaged Business Enterprise Participation to Ensure Compliance with the “Commercially Useful Function” RequirementsX 
910.5Conduct Interviews When Project Utilizes On-the-Job Trainees. Complete CDOT Form 1337 – Contractor Commitment to Meet OJT Requirements.Complete CDOT Form 838 – OJT Trainee / Apprentice Record.Complete CDOT Form 200 – OJT Training QuestionnaireX 
91.6Check Certified Payrolls (Contact the Region EEO/Civil Rights Specialists for training requirements.)X 
910.7Submit FHWA Form 1391 – Highway Construction Contractor’s Annual EEO ReportX 
 Finals
 11.1Conduct Final Project Inspection. Complete and submit CDOT Form 1212 – Final Acceptance Report (Resident Engineer with mandatory Local Agency participation.) X
1011.2Write Final Project Acceptance LetterX 
1011.3Advertise for Final SettlementX 
1111.4Prepare and Distribute Final As-Constructed PlansX 
1111.5Prepare EEO Certification and Collect EEO FormsX 
1111.6Check Final Quantities, Plans, and Pay Estimate; Check Project Documentation; and submit Final CertificationsX 
1111.7Check Material Documentation and Accept Final Material Certification (See Chapter 9)X 
1111.8Obtain CDOT Form 1419 from the Contractor and Submit to the CDOT Project ManagerX 
 11.9(FHWA Form 47 discontinued)X 
 11.10Complete and Submit CDOT Form 1212 – Final Acceptance Report (by CDOT) X
1111.11Process Final Payment X
 11.12Complete and Submit CDOT Form 950 – Project Closure X
1111.13Retain Project Records for Three Years from Date of Project Closure X
1111.14Retain Final Version of Local Agency Contract Administration ChecklistX 

cc:

  • CDOT Resident Engineer/Project Manager
  • CDOT Region Program Engineer
  • CDOT Region EEO/Civil Rights Specialist
  • CDOT Region Materials Engineer
  • CDOT Contracts and Market Analysis Branch
  • Local Agency Project Manager