Citizen Advisory Committee – October 2, 2024: El Paso County Monthly Change Order and Property Acquisition Report

To:

  • Pikes Peak Rural Transportation Authority Board of Directors
  • Pikes Peak Rural Transportation Authority Citizen Advisory Committee

From: Joshua J. Palmer P.E., County Engineer

Date: October 09, 2024

Re: PPRTA (2015-2024) Property Acquisition Status Report


The following is a summary and status of property acquisition efforts relative to design and/or construction of PPRTA 2 (2015-2024) projects for El Paso County Department of Public Works. A complete list of project specific property acquisition statuses is included as well.

  • 7 Projects – property acquisition COMPLETE
  • 5 Projects – property acquisition IN PROGRESS
  • 1 Project – scope of work does not require property acquisition (Stapleton Drive/Briargate Parkway)

El Paso County Capital Projects Property Acquisition Status (2015 – 2024)

Project NameStatus of ProjectStatus of Property AcquisitionTotal Number of Parcel Acquisitions Required for ProjectTotal Number of Parcel Acquisitions Still Pending NegotiationTotal Number of Parcels Acquired by Eminent Domain (Condemnation)Total Number of Parcels DonatedTarget to Complete all AcquisitionsTotal Acquisition Cost to Date (Does not include Consultant fees)
Beacon Lite RoadDesignIn progress313204th Quarter 2024$1,137,730.00
Black Forest Road (joint w/ City of Colorado Springs)City of Colorado Springs Led Project
Deer Creek, Base Camp, Microscope Way (aka Emigrant)DesignIn progress212100 
Eastonville RoadDesignIn progressTBDTBD00 
Fontaine Blvd/Security Blvd/Widefield Blvd IntersectionDesignComplete6000Complete
Highway 105 
  Project A – Interstate 25 to Lake Woodmoor DrConstructionComplete16000Complete
  Project B – Lake Woodmoor to MartingaleDesignNot StartedTBDTBDTBDTBDTBD 
Main St/Security BlvdConstructionComplete0000Complete
Old Meridian/McLaughlin RoundaboutConstructionComplete20002Complete$427,748.00
Mesa Ridge ParkwayDesignIn progress109011st Quarter 2025
Monument Hill RoadComplete (2018)Complete11001 $104,500.00
New Meridian/US 24 Int.ConstructionComplete17000Complete$914,220.00
South Academy BlvdConstructionComplete1000Complete
Stapleton Drive/Briargate Blvd Corridor Study (joint w/ City of Colorado Springs)N/AN/AN/AN/AN/AN/AN/AN/A
Tutt Blvd Extension (joint w/ City of Colorado Springs)City of Colorado Springs Led Project
West Colorado Avenue (joint w/ City of Manitou Springs/City of Colorado Springs)Complete (2021)In progress104122TBD$3,061,721.44