To:
- Pikes Peak Rural Transportation Authority Board of Directors
- Pikes Peak Rural Transportation Authority Citizen Advisory Committee
From: Joshua Palmer P.E., County Engineer, El Paso County Department of Public Works
Date: October 9, 2024
Re: Design of the Baptist / Hodgen / Roller Coaster Road Intersection Project
El Paso County requests approval to award a contract and purchase order with AECOM Technical Services, Inc. (AECOM) in the amount of $795,212.00 for engineering design services for the Baptist and Hodgen Rd at Roller Coaster Rd Intersection Improvements Project (also referred to as Baptist Roller Coaster).
The project site is located at the intersection of Baptist/Hodgen Road and Roller Coaster Road (the intersection) in Black Forest. The project includes the four approaches to the intersection.
The project will generally consist of improving safety and level of service to the intersection. An analysis of the intersection will be conducted to determine the best option. The design will include geometric, drainage, and traffic control improvements.
AECOM will complete the project through a series of project phases. This Scope of Services includes the Preliminary Design (60%), Final Design (90%), and Construction Documents (100%). Funds for this contract will come from the PPRTA Capital Funds Account 06-20-5460001 for the El Paso County Department of Public Works.
CONTRACT
Project: Design of the Baptist and Hodgen Rd at Roller Coaster Rd Intersection Improvements Project
Contract Amount: PPRTA: $795,212.00
Type: (Choose all that apply)
- ☒ Capital
- ☐ Maintenance
- ☐ Transit
- ☒ Consultant
- ☐ Equipment
- ☐ Construction
- ☐ Materials
- ☐ Personnel
- ☐ Other (description):
Project Description: The intersection improvements project includes providing Construction Documents (100% design) of the preferred design alternative to improve safety and level of service to the intersection.
Funds for this contract will come from the PPRTA Capital Funds Account 06-20-5460001 for the El Paso County Department of Public Works.
VENDOR INFORMATION
Vendor: AECOM Technical Services, Inc
Contract No.: CON #24-071
Contract Term (start/end dates) / Duration: Date approved by PPRTA Board and El Paso County Board of County Commissioners until completion of project
FINANCIAL INFORMATION
| Budget Category | Project Category | Contract Amount | Funds Available | 2025 Budget Amount | Budget Code |
|---|---|---|---|---|---|
| ☒ Capital ☐ Maintenance ☐ Transit | $795,212.00 | $1,000,000 | $8,200,000 | 06-20-5460001 | |
| Comments: Funds available equals total funding amount defined in resolution 24-180. | |||||
AWARD PROCESS
- ☒ IFB (Invitation for Bid)
- ☐ RFP (Request for Proposal)
- ☐ Sole Source
- ☐ Other
Comments: Through a competitive RFP process, seven (7) bids were received from: Alfred Benesch & Co, Mead & Hunt, AECOM, Matrix, Olsson, Stanley Consultants, and RockSol. AECOM was determined to be the best value
Attachments:
- ☒ Supporting Documentation
- ☐ Award Process Document
- ☒ Location Map

The map shows the project location for intersection improvements at the intersection of Baptist Road, Hodgen Road and Rollercoaster Road. The map shows the location with Interstate 25 to the west and Colorado Highway 83 to the east.