Citizen Advisory Committee – October 2, 2024: 2024 Capital, Maintenance and Public Transportation Contracts – El Paso County, Baptist / Hodgen / Roller Coaster Road Intersection Project

To:

  • Pikes Peak Rural Transportation Authority Board of Directors
  • Pikes Peak Rural Transportation Authority Citizen Advisory Committee

From: Joshua Palmer P.E., County Engineer, El Paso County Department of Public Works

Date: October 9, 2024

Re: Design of the Baptist / Hodgen / Roller Coaster Road Intersection Project


El Paso County requests approval to award a contract and purchase order with AECOM Technical Services, Inc. (AECOM) in the amount of $795,212.00 for engineering design services for the Baptist and Hodgen Rd at Roller Coaster Rd Intersection Improvements Project (also referred to as Baptist Roller Coaster).

The project site is located at the intersection of Baptist/Hodgen Road and Roller Coaster Road (the intersection) in Black Forest. The project includes the four approaches to the intersection.

The project will generally consist of improving safety and level of service to the intersection. An analysis of the intersection will be conducted to determine the best option. The design will include geometric, drainage, and traffic control improvements.

AECOM will complete the project through a series of project phases. This Scope of Services includes the Preliminary Design (60%), Final Design (90%), and Construction Documents (100%). Funds for this contract will come from the PPRTA Capital Funds Account 06-20-5460001 for the El Paso County Department of Public Works.


CONTRACT

Project: Design of the Baptist and Hodgen Rd at Roller Coaster Rd Intersection Improvements Project

Contract Amount: PPRTA: $795,212.00

Type: (Choose all that apply)

  • ☒ Capital
  • ☐ Maintenance
  • ☐ Transit
  • ☒ Consultant
  • ☐ Equipment
  • ☐ Construction
  • ☐ Materials
  • ☐ Personnel
  • ☐ Other (description):

Project Description: The intersection improvements project includes providing Construction Documents (100% design) of the preferred design alternative to improve safety and level of service to the intersection.

Funds for this contract will come from the PPRTA Capital Funds Account 06-20-5460001 for the El Paso County Department of Public Works.

VENDOR INFORMATION

Vendor: AECOM Technical Services, Inc
Contract No.: CON #24-071
Contract Term (start/end dates) / Duration: Date approved by PPRTA Board and El Paso County Board of County Commissioners until completion of project

FINANCIAL INFORMATION

Budget CategoryProject CategoryContract AmountFunds Available2025 Budget AmountBudget Code
☒ Capital
☐ Maintenance
☐ Transit
$795,212.00$1,000,000$8,200,00006-20-5460001
Comments: Funds available equals total funding amount defined in resolution 24-180.

AWARD PROCESS

  • ☒ IFB (Invitation for Bid)
  • ☐ RFP (Request for Proposal)
  • ☐ Sole Source
  • ☐ Other

Comments:  Through a competitive RFP process, seven (7) bids were received from: Alfred Benesch & Co, Mead & Hunt, AECOM, Matrix, Olsson, Stanley Consultants, and RockSol. AECOM was determined to be the best value

Attachments:

  • ☒ Supporting Documentation
  • ☐ Award Process Document
  • ☒ Location Map
Site map showing the construction location at the intersection of Baptist Road, Hodgen Road and Roller Coaster Road

The map shows the project location for intersection improvements at the intersection of Baptist Road, Hodgen Road and Rollercoaster Road. The map shows the location with Interstate 25 to the west and Colorado Highway 83 to the east.