Logo of the Pikes Peak Rural Transportation Authority with the tagline Promises Made, Promises Kept

719-471-7080

Citizen Advisory Committee – October 2, 2024: 2024 Capital, Maintenance and Public Transportation Contracts: City of Colorado Springs – Rustic Hills – Halfmoon Paving

To:

  • Pikes Peak Rural Transportation Authority (PPRTA) Board of Directors
  • Pikes Peak Rural Transportation Authority Citizen Advisory Committee (CAC)

From: City of Colorado Springs – Tyra Sandy, PE, Senior Engineer

CC: City of Colorado Springs – Gayle Sturdivant, PE, PMP, City Engineer/ Deputy Public Works Director

Date: October 2, 2024


CONTRACT

Project: Rustic Hills – Halfmoon Paving (Maintenance Project # 03-30-5231000)

Contract Amount: PPRTA: $482,608.25, Other: $0.00

Type: (Choose all that apply)

  • ☐ Capital
  • ☒ Maintenance
  • ☐ Transit
  • ☐ Consultant
  • ☐ Equipment
  • ☒ Construction
  • ☐ Materials
  • ☐ Personnel
  • ☐ Other (description):

Project Description: The Rustic Hills Halfmoon Paving project is in the Rustic Hills Subdivision southeast of the intersection of Constitution Ave and N Murray Blvd (location map attached). The project consists of paving the last remaining dirt segment on Halfmoon Rd to reducing long-term maintenance costs. There were two previous projects within Rustic Hills to complete the paving. Halfmoon Drive was previously included in Rustic Hills Phase II. However, it was removed from the project as CSU needed to upgrade the water line beneath the roadway.

The City informally advertised the project for construction August 7, 2024. Bids were opened on August 20, 2023, and two (2) bids were received. Bids received are as follows:

BidderMartin MarittaESI
Base Bid$798,684.60$482,608.25

Selection is based on lowest base bid, which was $482,608.25. The base bid is under the engineers estimate.

The City requests the PPRTA Board approve a contract with Elite Surface Infrastructure (ESI) for the bid amount of $482,608.25.

VENDOR INFORMATION

Vendor: Elite Surface Infrastructure (ESI)
Contract No.: R-11094 Task Order 2024-002
Contract Term (start/end dates) / Duration: Notice to Proceed/December 31, 2024

FINANCIAL INFORMATION

Budget CategoryProject CategoryContract AmountFunds Available2024/25 Budget AmountBudget Code
Rustic Hills Phase II☐Capital
☒Maintenance
☐Transit
$482,608.25$6,198,399$25,737,65503-30-5231000
Comments: 

AWARD PROCESS

  • ☒ IFB (Invitation for Bid)
  • ☐ RFP (Request for Proposal)
  • ☐ Sole Source
  • ☐ Other

Comments: A Request for Informal Quote was solicited to the On Call 2C2 Asphalt vendors. Two quotes were received.

Attachments:

  • ☒ Location Map
  • ☐ Award Process Document
  • ☐ Final Design Scope and Fee
A map showing the location of Half Moon Drive circled in blue.

The map shows the location of Half Moon Drive, circled in blue, in Colorado Springs.