Logo of the Pikes Peak Rural Transportation Authority with the tagline Promises Made, Promises Kept

719-471-7080

Citizen Advisory Committee – October 2, 2024: 2024 Capital, Maintenance and Public Transportation Contracts: City of Colorado Springs – Academy Blvd Reconstruction

To:

  • Pikes Peak Rural Transportation Authority (PPRTA) Board of Directors
  • Pikes Peak Rural Transportation Authority Citizen Advisory Committee (CAC)

From: City of Colorado Springs – Scott Vinton, Project Manager

CC: City of Colorado Springs – Gayle Sturdivant, PE, PMP, City Engineer/ Deputy Public Works Director

Date: October 2, 2024


CONTRACT

Project:

  • Academy Blvd – Bijou St to Airport Rd (PPRTA Capital Project 03-20-5030002)
  • Academy Blvd – Fountain Blvd to Milton E Proby Pkwy (PPRTA Capital Project 03-20-5030003)

Contract Amount: PPRTA: $28,581,059.61, Other: $419,142.16 CSU

Type: (Choose all that apply)

  • ☒ Capital
  • ☐ Maintenance
  • ☐ Transit
  • ☐ Consultant
  • ☐ Equipment
  • ☒ Construction
  • ☐ Materials
  • ☐ Personnel
  • ☐ Other (description)

Project Description: The Academy Boulevard Reconstruction from Bijou Street to Airport Road (north segment) and from Fountain Boulevard to Milton E Proby Parkway (south segment) are PPRTA ‘A’ list projects. Academy Boulevard is a six-lane road with poor pavement quality and deteriorated curb, gutter, and medians requiring replacement. Poor drainage is contributing to pavement decline, so a new storm water system is being designed to alleviate ponding issues. Planned improvements incorporate a 10-foot- wide multi-use path.

The City and PPRTA awarded Ames Construction, Inc. the contract following the July 23, 2022, Board meeting.

Ames will continue to work on the North Segment to completion. The City has decided to descope the remaining South Segment work from Ames’ contract. Ames will be paid for the work completed per the terms of the contract.

The City requests the PPRTA Board approve a construction change order for Ames Construction, Inc. reducing the contract by $29,000,201.77.

The revised contract amount for the work performed is $33,483,555.23 as outlined in the following table.

ContractN 03-20-5030002S 03-20-503003CSUAmount
T-10909$14,575,300.00$40,632,590.00$4,289,910.00$59,497,800.00
Change Order 1$0.00$2,235,593.00$750,364.00$2,985,957.00
Change Order 2$0.00$0.00 $0.00 $0.00
Change Order 3-$2,862,526.00-$25,718,533.61-$ 419,142.16$-29,000,201.77
Total   $33,483,555.23

VENDOR INFORMATION

Vendor: Ames Construction, Inc. 
Contract No.: T – 10909
Contract Term (start/end dates) / Duration: Contract Execution – July 23, 2022 to December 31, 2024

FINANCIAL INFORMATION

Budget CategoryProject CategoryChange Order AmountFunds Available2024 Budget AmountBudget Code
Academy Blvd: Fountain to Proby☒Capital
☐Maintenance
☐Transit
($25,718,533.61)  $1,633,828  $13,300,000  03-20-5030003
Academy Blvd: Bijou to Airport☒Capital
☐Maintenance
☐Transit
($2,862,526)$280,266$0.0003-20-5030002
CSU Academy to Jet WingOther($224,778.16)$1,257,834$0.00202-3100-9310314
CSU South Academy – MPP to FountainOther($194,364.00)$0.00$0.00202-3100-9310317
Total ($29,000,201.77)   
Comments:     

AWARD PROCESS

  • ☒ IFB (Invitation for Bid)
  • ☐ RFP (Request for Proposal)
  • ☐ Sole Source
  • ☐ Other

Comments: Wildcat Construction has an approved On-Call Bridge Maintenance contract for 2024. The On-Call was selected via RFP. Four contractors submitted on the on-call and four were selected.

Attachments:

  • ☐ Location Map
  • ☐ Award Process Document
  • ☐ Final Design Scope and Fee