Citizen Advisory Committee – November 6, 2024: Financial Reports: Sales and Use Tax Report – 2024 Revenue and Expense Summary

Pikes Peak Rural Transportation Authority
Revenue and Expense Summary
For Year End December 31, 2024
September 16, 2024
Modified Cash Basis
(in dollars)

CategoryYear-to-date ActualYear-to-date BudgetPercent of YTD BudgetAnnual Budget Including Estimated CarryoverActual Difference from Annual BudgetAnnual Percent of Budget ExpendedNotes
Revenue
Total Tax Revenue103,032,55198,085,724105%150,000,000(49,967,449)69%1
Other Revenue Sources:
Public Transportation fare & advertising revenue1,684,8611,908,08988%2,862,133(1,177,272)59% 
Interest Earnings14,340,94712,000,000120%16,000,000(1,659,053)90% 
Gross Revenue119,058,360111,993,813106%168,862,133(49,803,773)71% 
Sales and Use tax collection costs(108,728)(180,000)60%(270,000)161,27240% 
Net Revenue118,949,632111,831,813106%168,592,133(49,642,501)71% 
Expenditures
Administrative451,1631,612,89428%2,146,5251,695,36221% 
Public Transportation12,680,63045,214,93428%60,286,57847,605,94821%
Maintenance       
Town of Green Mountain Falls 59,2720%79,87479,8740% 
City of Manitou Springs 274,416327,43884%441,247166,83162%
City of Colorado Springs26,418,17043,523,84061%58,651,55232,233,38245% 
El Paso County10,81,95617,311,88663%23,329,03112,347,07547%
Town of Ramah 43,1470%58,14458,1440% 
Town of Calhan57,7260%77,79077,790 0%
 37,674,5425,863,648643%82,637,63844,963,09646% 
Capital
Initial “A” list projects
City of Colorado Springs
Roadway Safety and Traffic Operations 0#DIV/0!00#DIV/0! 
Pikes Peak Greenway Improvements 0#DIV/0!00#DIV/0! 
Marksheffel Road (PAFB to Black Forest)(116,855)9,506-1229%9,506126,361-1229% 
 (116,855)9,506-1229%9,506126,361-1229% 
El Paso County
Meridian Rd Ext. (Falcon to US 24) 08980%8988980%
08980%8988980% 
Total for Initial “A” list(116,855)10,404-1123%10,404127,259-1123%
Capital Renewal “A” list Projects
Town of Green Mountain Falls
Belvidere Avenue 0#DIV/0!00#DIV/0! 
Stilling Basins(24,828)0#DIV/0!024,828#DIV/0! 
 (24,828)0#DIV/0!024,828#DIV/0! 
City of Manitou Springs
Manitou Avenue W. End Ped & Drainage Improvements2,34042,4506%55,26752,9274% 
Manitou Downtown Sidewalk, Drainage & Utilities 0161,8410%215,788215,7880% 
W. Co. Ave. reconstruction: 31st St. to US 24 Joint project –0#DIV/0!00#DIV/0! 
Transit Shuttle Parking24,7691,491,1642%1,988,2191,988,2191% 
 27,1091,694,4562%2,259,2742,232,1651% 
City of Colorado Springs
8th St. Imps.: Motor City Way to Fountain Creek346,5263,125,50411%4,164,6723,8181468% 
Academy Blvd. Bijou St. to Airport Rd Reconstruction5,696,2487,837,69473%10,450,2584,754,01055% 
Academy Blvd. Fountain to Proby Pkwy Reconstruction4,438,25230,374,04415%40,498,72536,060,47311% 
Academy Over Cottonwood Creek Bridge Rehab. (2,926)0#DIV/0!02,926#DIV/0! 
Airport Rd. over Spring Creek Bridge replacement 00#DIV/0!00#DIV/0! 
Barnes Rd-Solar Ridge to Powers Blvd. 0#DIV/0!00#DIV/0! 
Black Forest Rd.-Woodmen to Research (Joint Project)6,655,4397,175,96793%9,567,9562,912,51770% 
Centennial Blvd. Ext.: Fillmore-Fontanero192,685351,00755%468,009275,32441% 
Centennial: G. of G. to Fillmore Pavement Reconstruction 3,7500%5,0005,0000% 
Chestnut over S.Douglas Creek Bridge Replacement 0#DIV/0!00#DIV/0! 
Circle Drive projects combined12,485,38829,797,25742%39,729,67627,244,28831% 
Circle Drive EB over Fountain Creek Bridge Replacement 0#DIV/0!00#DIV/0! 
Circle Drive EB over Hancock Bridge Rehabilitation 0#DIV/0!00#DIV/0! 
Circle Drive WB over Fountain Bridge Rehabilitation 0#DIV/0!00#DIV/0! 
Circle Drive WB over Hancock Bridge Rehabilitation 0#DIV/0!00#DIV/0! 
Companion Drainage Improve. for roadway Projects60,834309,00020%412,000351,16615% 
Dublin Rd.: Bridle Pass Way to Powers Blvd. 0#DIV/0!00#DIV/0! 
El Paso Bridge Over Fountain Creek Tributary Replacement493,514549,64190%732,854239,34067% 
Emergency Bridge Fund216,2996,064,4414%8,085,9217,869,6223% 
Enchanted Circle Over Sand Creek Bridge Replacement 0#DIV/0!00#DIV/0! 
Galley Rd. over Sand Creek Bridge Replacement(260,779)3,226,874-8%4,302,4984,563,277-6% 
I-25 Ramps: S. Nevada/Tejon St. Corridor Improvements2,288,7906,170,75937%8,227,6795,938,88928% 
Las Vegas St./Royer UPRR Crossing Relocation201,2559,938,5312%13,251,37513,050,1202% 
Midland Trail Improvements: Ridge Rd. to Columbia St. 0#DIV/0!00#DIV/0! 
Old Ranch Rd. Improvements & Bridge Reconstruction 2#DIV/0!330% 
Pikes Peak Ave: Colo. To Printers Pkwy Reconstruction 9,4830%12,64412,6440% 
Platte Ave. Connection to I-25 Study 0#DIV/0!00#DIV/0! 
Platte-W. Bound over Sand Creek Bridge Replacement35,68365,96254%87,94942,26641% 
Rock Island Trail Corridor Improvements 749,9960%999,995999,9950% 
S. Cheyenne Canyon Rd over Creek Bridge Replacement2,443,2662,100,642116%2,800,856357,59087% 
Shook’s Run Bridge Corridor Improvement Study 32,1830%42,91142,9110% 
Shook’s Run Trail corridor Improvements 600,0000%800,000800,0000% 
Stapleton Dr./Briargate Blvd Corridor Study (Joint project) 00#DIV/0!00#DIV/0! 
Tutt Blvd Extension: Dublin to Templeton Gap1,730,0432,776,75862%3,702,3441,972,30147% 
Union Pacific RR: Mainline over Fontanero Bridge Replace126,59715,086,4751%20,115,30019,988,7031% 
Union Pacific RR: Nevada & Tejon Crossing -design only2421,683,0170%2,244,0232,243,7810% 
W. Fillmore over Unnamed Channel Bridge Replacement2,009,8751,994,5885%2,659,451649,57676% 
W. Co. Ave. reconstruction: 31ST ST. TO US 24 Joint proj. 056,6280%75,50475,5040% 
Woodmen Rd Improve.: Union Continuous Flow Intersection8,189170,4595%227,279219,0904% 
Pikes Peak Greenway Corridor Improvements646,2501,487,48143%1,983,3081,337,05833% 
Platte Ave. Corridor Improvement Study8,45014,35459%19,13910,68944% 
Sinton Trail Corridor Improvements0390,6390%520,852520,8520% 
Templeton Gap Trail Corridor Improvements 359,828431,25083%575,000215,17263% 
Citywide Capital
Citywide Intersection Improvement Ph. I5,671,0556,665,65185%8,887,5343,216,47964% 
Citywide On-Street Bikeway Improvements-Ph. I29,780989,1473%1,318,8621,289,0822% 
Citywide Ped Transportation Improvements-Ph. I44,2681,395,7373%1,860,9831,816,7152% 
Citywide Roadway Safety, Traffic Ops, & Maint. Ph. I12,294,21415,543,02179%20,724,0288,429,81459% 
Citywide School & Neighborhood Ped Improvements Ph. I196,96316,68338%688,910491,94729% 
Citywide Congestion and Incident Mgmt. Signal Imp. Ph. I216,854920,90724%1,227,8761,011,02218% 
Citywide Traffic Signal System Upgrade 0451,7030%602,270602,2700% 
Transit Capital
ADA-Par transit Bus system Vehicle Replacement 0#DIV/0!00#DIV/0! 
Fixed-Route Bus System Vehicle Replacement 3,986,9990%5,315,9985,315,9980% 
Sidewalk/Bus stop program- Existing Routes 230,3190%307,092307,0920% 
Vanpool Vehicle Replacement 0#DIV/0!00#DIV/0! 
 58,633,082163,272,55136%217,696,734159,063,65227% 
EL Paso County
Beacon Lite Road-Highway 105 to County Line Rd.605,71016,484,2404%21,978,98621,373,2763%
Deer Creek, Base Camp, Microscope Way (Emigrant Trail)204,0473,344,5666%4,459,4214,255,3745%
Eastonville Road-McLaughlin Rd. to Latigo Blvd.138,42012,711,1401%16,948,18616,809,7661%
Fontaine Blvd at Security Blvd At Widefield Rd 0314,0150%418,686418,6860%
Highway 105: I25 to Highway 832,471,89016,115,35115%21,487,13519,015,24512%
Main St. at Security Blvd.00#DIV/0!00#DIV/0!
Meridian/McLaughlin Roundabout 0115,5650%154,086154,0860%
Mesa Ridge Parkway: Powers to Marksheffel21,7796,411,4270%8,548,5698,526,7900%
Monument Hill Road: County Line to Woodmoor0229,7150%306,286306,2860%
New Meridian/US-242,0201,524133%2,0321299%
S. Academy Blvd-I-25 to Bradley Rd Ramps19,333,16244,395,84844%59,194,46439,861,30233%
Stapleton Dr./Briargate Blvd. Corridor Study (Joint Project) 00#DIV/0!00#DIV/0!
Tutt Blvd Extension Dublin to T-Gap (Joint project)416,2500%555,000555,0000%
West Colorado Ave (Joint project) 02,4560%3,2743,2740%
 22,777,028100,542,09423%134,056,125111,279,09717%
Town of Ramah
Ramah Street Overlay project 30,00028,776104%38,3688,36878%
Total ‘renewal Capital “A” list funding81,442,391265,537,87631%354,050,501272,608,11023% 
Total Capital Expenditures81,325,536265,548,28031%354,060,905272,608,11023% 
Total Projects and Transportation expenses131,680,707316,626,86142%496,985,121365,304,41426% 
Total Expenditures132,131,870318,239,755342%499,131,646366,999,77626% 
Revenue Over/(Under) Expenditures(13,182,238)(206,425,941)6%(330,539,513)(416,642,277)4% 
Beginning fund balance0330,597,475 330,597,475330,597,475  
Net Activity including prior year carryover(13,182,238)124,171,534-11%57,962(86,044,802)  
Reserves:       
Reduction to Reserve(29,160)(29,160)100%(57,962)(28,802)50% 
Net Reserve balance adjustment(29,160)(29,160)100%(57,962)(28,802)50% 
Net Activity Less Reserve adjustment($13,21,398)$124,142,374-11%$0($13,211,398)N/A 

Notes:
1: Tax revenues from the State are received by the PPRTA two months in arrears. This statement includes August sales and use tax received in October 2024.