Citizen Advisory Committee – November 6, 2024: Financial Reports: Capital Expenditure Reports

Pikes Peak Rural Transportation Authority
Capital Expenditures Report
Actual At October 14, 2024

ProjectAmount Spent to dateProject BudgetUnder/(over) Budget% Spent
City of Colorado Springs    
Austin Bluffs Interchange$35,981,318$35,981,318$0100.00%
Cimarron Street Bridge8,050,8708,050,8700100.00%
Austin Bluffs/Nevada Improvements4,156,4784,156,4780100.00%
I-25 Interchange Companion Projects2,243,7202,243,7200100.00%
Fillmore/Union Improvements2,117,3992,117,3990100.00%
Academy/Fountain Safety Improvement917,400917,4000100.00%
30th Street Corridor Safety Improvements36,53136,5310100.00%
Union/Palmer Park Improvements150,817150,8170100.00%
Constitution/Circle Drive Improvements1,518,2881,518,2880100.00%
Fillmore Street- Templeton Gap to Hancock607,798607,7980100.00%
Fillmore Street/El Paso Street Improvements497,329497,3290100.00%
Constitution/Chelton Rd Improvements27,55027,5500100.00%
Academy Blvd/Pikes Peak Improvements962,941962,9410100.00%
Powers Blvd Right-of-Way Protection/Acquisition6,105,0916,105,0910100.00%
Woodmen Road Widening & Interchange39,191,13639,191,1360100.00%
South Metro Accessibility, Phase I52,708,78652,708,7860100.00%
Austin Bluffs Corridor Improvements (Nevada to Academy)27,027,03427,027,0340100.00%
Austin Bluffs Corridor Improvements (Barnes to Old Farm)4,805,6004,805,6000100.00%
Vincent Drive Bridge5,803,0375,803,0370100.00%
Hancock Avenue Bridge4,848,9524,848,9520100.00%
Vincent Drive Extension8,679,9328,679,9320100.00%
Fillmore Street Corridor (I-25 to Centennial)7,088,7377,088,7370100.00%
Austin Bluffs Bridge Widening (at Cottonwood Creek)4,075,5874,075,5870100.00%
25th Street Bridge136,492136,4920100.00%
Garden of the Gods/Chestnut Improvements431,972431,9720100.00%
Congestion/Incident Management Signal Improvement2,599,4552,599,4550100.00%
Roadway Safety and Traffic Operations11,589,24911,589,2490100.00%
On-Street Bikeway Improvements1,116,5441,116,5440100.00%
Pikes Peak Greenway Improvements1,253,2871,253,2870100.00%
Marksheffel Road Widening & Extension (PAFB to Black Forest)5,479,9705,634,395154,42597.26%
 240,209,301240,363,725154,42599.94%
City of Manitou Springs    
Manitou Avenue Improvements3,003,1243,003,1240100.00%
Town of Green Mountain Falls    
Ute Pass Avenue Widening304,320304,3200100.00%
El Paso County    
Baptist-Hodgen Connection2,062,0032,062,0030100.00%
Baptist Road Widening (I-25 to Tari Drive)8,568,0998,568,0990100.00%
Struthers Extension/Jackson Creek3,714,5003,714,5000100.00%
Akers Drive1,714,6151,714,6140100.00%
South Metro Accessibility, Phase I25,017,19125,017,1910100.00%
Stapleton/Judge Orr Extension (Eastonville to US 24)2,343,2682,343,2680100.00%
Meridian Road Extension (Falcon Hwy to US 24)752,787753,68589899.88%
County Line Road Upgrade7,031,5627,031,5620100.00%
Meridian Road Widening (Woodmen to Rex Rd)7,465,5697,465,5690100.00%
Hodgen Road Upgrade to Arterial19,047,92019,047,9200100.00%
Marksheffel Road Widening & Extension (PAFB to Black Forest)18,526,86818,534,5127,64499.96%
Baptist Road Widening-Mitchell to I-25 (combined below)0001#DIV/0!
Baptist RR Crossing amd Baptist Road Widening-Mitchell to I-2511,065,39911,065,39901100.00%
Marksheffel Road Widening (Mesa Ridge to SH 94)32,010,59032,010,5900100.00%
Stapleton/Judge Orr Extension (US 24 to Curtis Rd)4,970,7354,970,7350100.00%
 144,291,106144,299,6478,54299.99%
Total Capital Expenditures$387,807,850$387,970,816$162,96699.96%

Notes:

  1. Baptist Rd Widening and RR crossing are combined projects

Pikes Peak Rural Transportation Authority
Capital Expenditure Report-renewal 2nd ten years
Actual At September 16, 2024

ProjectAmount Spent to-DateOriginal Project costEst. Revised Project CostEst. Under/(over) current Estimate% spent
CITY OF COLORADO SPRINGS
8TH ST. IMPS.: MOTOR CITY WAY TO FOUNTAIN CREEK758,9381,500,0004,577,0833,818,14517%
ACADEMY BLVD.: BIJOU ST. TO AIRPORT RD. PAVEMENT RECONSTRUCTION11,231,7233,817,0015,985,7344,754,01170%
ACADEMY BLVD.: FOUNTAIN TO MILTON PROBY PKWY. PAVEMENT RECONSTRUCTION14,968,85815,200,00049,029,33134,060,47331%
ACADEMY OVER COTTONWOOD CREEK BRIDGE REHABILITATION9,130,4091,280,0009,180,00049,59199%
AIRPORT RD. OVER SPRING CREEK BRIDGE REPLACEMENT5,573,2011,584,0006,159,595586,39490%
BARNES RD. ROADWAY IMPROVEMENTS, SOLAR RIDGE DR. TO POWERS BLVD.4,050,0002,420,0004,050,000–100%
BLACK FOREST RD. ROADWAY IMPROVEMENTS: WOODMEN TO RESEARCH (JOINT PROJ)27,881,4538,866,00042,380,76914,499,31666%
CENTENNIAL BLVD. EXTENSION: FILLMORE TO FONTANERO26,355,30610,450,00026,630,629275,32399%
CENTENNIAL ST.: GARDEN OF THE GODS TO FILLMORE PAVEMENT RECONSTRUCTION11,715,0288,065,00012,287,810572,78295%
CHESTNUT ST. OVER S. DOUGLAS CREEK BRIDGE REPLACEMENT4,162,9261,800,0004,162,926–100%
CIRCLE DR. EB OVER FOUNTAIN CREEK BRIDGE REHABILITATION16,139,7233,300,00011,301,000(4,838,723)143%
CIRCLE DR. EB OVER HANCOCK BRIDGE REHABILITATION1,938,5723,300,00011,301,0009,362,42817%
CIRCLE DR. WB OVER FOUNTAIN CREEK BRIDGE REHABILITATION–3,300,00011,301,00011,301,0000%
CIRCLE DR. WB OVER HANCOCK BRIDGE REHABILITATION–3,300,00011,301,00011,301,0000%
COMPANION DRAINAGE IMPROVEMENTS FOR ROADWAY PROJECTS3,768,8042,690,0003,708,000(60,804)102%
DUBLIN RD. IMPROVEMENTS: BRIDLE PASS WAY TO POWERS BLVD.1,932,8721,540,0002,029,16596,29395%
EL PASO BRIDGE OVER FOUNTAIN CREEK TRIBUTARY REPLACEMENT1,258,260457,0001,497,600239,34084%
EMERGENCY BRIDGE FUND12,171,0165,381,00020,040,6387,896,62261%
ENCHANTED CIRCLE OVER SAND CREEK TRIBUTARY BRIDGE REPLACEMENT358,794300,000500,000141,20672%
GALLEY RD. OVER SAND CREEK BRIDGE REPLACEMENT1,143,1001,936,0005,706,3784,563,27820%
I-25 RAMPS: SOUTH NEVADA/ TEJON ST. CORRIDOR IMPROVEMENTS3,172,6075,500,0009,111,4975,938,89035%
LAS VEGAS ST./ROYER UPRR CROSSING RELOCATION1,705,1183,850,00014,755,23813,050,12012%
OLD RANCH RD. IMPROVEMENTS AND BRIDGE CONSTRUCTION8,599,9998,000,00010,031,6681,431,66986%
PIKES PEAK AVE. : COLORADO TO PRINTERS PKWY. PAVEMENT RECONSTRUCTION15,850,1118,663,00016,077,754227,64399%
PLATTE AVE. CONNECTION TO I-25 STUDY–550,000550,000550,0000%
PLATTE AVE. CORRIDOR IMP. STUDY1,989,3112,200,0002,000,00010,68999%
PLATTE AVE. WB OVER SAND CREEK BRIDGE REPLACEMENT4,491,7345,874,0004,634,000142,26697%
S. CHEYENNE CANYON RD. 1 OVER CHEYENNE CREEK BRIDGE REPLACEMENT3,110,308410,0003,467,898357,59090%
SHOOK’S RUN BRIDGE CORRIDOR STUDY2,707,0902,750,0002,750,00042,91098%
STAPLETON DR. /BRIARGATE BLVD. CORRIDOR STUDY (JOINT PROJ)106,054786,000420,054314,00025%
TUTT BLVD. EXTENSION: DUBLIN TO TEMPLETON GAP RD. (JOINT PROJ)3,307,2171,393,0004,724,5181,417,30170%
UPRR MAINLINE OVER FONTANERO BRIDGE REPLACEMENT1,389,0922,750,00022,716,46021,327,3686%
UPRR NEVADA & TEJON ST. CROSSING RECONSTRUCTION (DESIGN ONLY)2,806,2193,300,0005,050,0002,243,78156%
W. COLORADO AVE. RECONSTRUCTION: 31ST ST. TO US 24 (JOINT PROJ)26,041,1278,600,00026,071,31030,183100%
W. FILLMORE OVER UNNAMED CHANNEL BRIDGE REPLACEMENT3,145,3941,000,0003,794,970649,57683%
WOODMEN ROAD IMPROVEMENTS: UNION CONTINUOUS FLOW INTERSECTION8,480,9187,500,0009,000,000519,08894%
COTTONWOOD TRAIL CORRIDOR IMPROVEMENTS600,000600,000600,000–100%
MIDLAND TRAIL IMPROVEMENTS: RIDGE RD. TO COLUMBIA ST.450,000450,000450,000–100%
PIKES PEAK GREENWAY CORRIDOR IMPROVEMENTS6,362,9412,121,0007,700,0001,337,05983%
ROCK ISLAND TRAIL CORRIDOR IMPROVEMENTS51,000,0001,000,000999,9950%
SHOOK’S RUN TRAIL CORRIDOR IMPROVEMENTS–800,000800,000800,0000%
SINTON TRAIL CORRIDOR IMPROVEMENTS304,148600,000825,000520,85237%
TEMPLETON GAP TRAIL CORRIDOR IMPROVEMENTS609,828600,000825,000215,17274%
ADA-PARATRANSIT BUS SYSTEM VEHICLE REPLACEMENT951,3421,400,0003,091,0512,139,70931%
FIXED-ROUTE BUS SYSTEM VEHICLE REPLACEMENT4,322,9394,700,0008,557,9174,234,97851%
SIDEWALK/BUS STOP PROG. EXISTING ROUTES (RAMPS, PADS, RT CHANGES, ENH.)231,7181,500,0002,020,0001,788,28211%
VANPOOL VEHICLE REPLACEMENT79,911800,0001,070,001990,0907%
CITYWIDE INTERSECTION IMPROVEMENTS PH I18,144,0896,171,00014,064,697(4,079,392)129%
CITYWIDE ON-STREET BIKEWAY IMPROVEMENTS PH I3,431,6463,027,0005,132,7271,701,08167%
CITYWIDE PEDESTRIAN TRANSPORTATION IMPROVEMENTS PH I6,408,9235,153,0007,833,6351,424,71282%
CITYWIDE ROADWAY SAFETY, TRAFFIC OPERATIONS, AND MAINTENANCE PH I29,544,1368,108,00027,976,876(1,567,260)106%
CITYWIDE SCHOOL AND NEIGHBORHOOD PEDESTRIAN IMPROVEMENTS PH I3,628,0243,027,0004,531,970903,94680%
CITYWIDE CONGESTION AND INCIDENT MANAGEMENT SIGNAL IMPROVEMENT PH I3,108,9483,027,0004,531,9701,423,02269%
CITYWIDE TRAFFIC SIGNAL SYSTEM UPGRADE (60 LOCATIONS)12,023,83314,983,00012,626,103602,27095%
TOTAL CITY OF COLORADO SPRINGS331,643,707201,679,000491,921,972160,278,26567%
CITY OF MANITOU SPRINGS
MANITOU AVE. WEST END PEDESTRIAN AND DRAINAGE IMPS1,581,195850,0001,600,00018,80599%
MANITOU SPRINGS DOWNTOWN SIDEWALK, DRAINAGE AND UTILITIES IMPS896,316768,0001,500,000603,68460%
MANITOU SPRINGS TRANSIT SHUTTLE AND SURFACE OR STRUCTURE PARKING1,195,631650,0001,901,281705,65063%
W. COLORADO AVE. RESCONSTRUCTION: 31ST ST. TO US 24 (JOINT PROJ)453,415150,000455,1231,708100%
TOTAL CITY OF MANITOU SPRINGS4,126,5572,418,0005,456,4041,329,84776%
TOWN OF GREEN MOUNTAIN FALLS
BELVEDERE AVE. WIDENING PH I197,168222,000226,00028,83287%
STILLING BASINS591,23488,000582,580(8,654)101%
TOTAL TOWN OF GREEN MOUNTAIN FALLS788,402310,000808,58020,17898%
EL PASO COUNTY
BEACON LITE RD. : HWY 105 TO COUNTY LINE RD.2,761,6174,361,00019,734,89216,973,27514%
BLACK FOREST RD. ROADWAY IMPROVEMENTS: WOODMEN TO RESEARCH (JOINT PROJ)–3,534,00030,793,97030,793,9700%
DEER CREEK, BASE CAMP, EMIGRANT: MONUMENT HILL TO WOODMOOR691,998200,0004,200,0003,508,00216%
EASTONVILLE RD. : MCLAUGHLIN TO LATIGO990,7948,525,00013,996,12313,005,3297%
FONTAINE BLVD. AT SECURITY BLVD. AND WIDEFIELD BLVD.1,331,3141,250,0001,500,000168,68689%
HIGHWAY 105: I25 TO HIGHWAY 8311,731,65418,314,00030,400,00018,668,34639%
MAIN ST. AT SECURITY BLVD.750,000750,000750,000–100%
MERIDIAN/MCLAUGHLIN ROUNDABOUT4,326,6982,376,0004,480,184153,48697%
MESA RIDGE PKWY. IMPS.: POWERS TO MARKSHEFFEL1,488,2079,975,00010,015,0008,526,79315%
MONUMENT HILL RD. : COUNTY LINE RD. TO WOODMOOR DR.4,877,5663,965,00011,683,8526,806,28642%
NEW MERIDIAN RD. AT US-244,520,3844,608,0005,103,816583,43289%
S. ACADEMY BLVD.: I25 TO BRADLEY RD. RAMPS27,177,99218,000,00055,539,29428,361,30249%
STAPLETON DR. /BRIARGATE BLVD. CORRIDOR STUDY (JOINT PROJ)333,175314,0001,100,000766,82530%
TUTT BLVD. EXTENSION: DUBLIN TO TEMPLETON GAP RD. (JOINT PROJ)–555,000555,000555,0000%
W. COLORADO AVE. RECONSTRUCTION: 31ST ST. TO US 24 (JOINT PROJ)10,468,489*3,428,00010,392,215(76,274)101%
TOTAL EL PASO COUNTY71,449,88880,155,000200,244,346128,794,45836%
TOWN OF RAMAH
RAMAH STREET OVERLAY PROGRAM112,58160,00082,584(30,000)136%
I-25 GAP JOINT PROJECT10,000,00010,000,000– 100%
GRAND TOTAL418,121,138284,622,000708,513,886290,392,74759%