Citizen Advisory Committee – July 3, 2024: El Paso County Monthly Change Order & Property Acquisition Report

To:

  • Pikes Peak Rural Transportation Authority Board of Directors
  • Pikes Peak Rural Transportation Authority Citizen Advisory Committee

From: Joshua Palmer P.E., County Engineer – El Paso County Department of Public Works

Date: July 10, 2024

Property Acquisition Report – July 2024

ProjectOwnerCounty Appraised ValueOwner Appraised ValueFinal Settlement ValueRight-of-WayEasements
Beacon Lite RoadBob E. Nance$4,050.00N/A$4,050.00 TE – 111

To:

  • Pikes Peak Rural Transportation Authority Board of Directors
  • Pikes Peak Rural Transportation Authority Citizen Advisory Committee

From: Joshua J. Palmer P.E., County Engineer

Date: July 10, 2024

Re: PPRTA (2015-2024) Property Acquisition Status Report                

The following is a summary and status of property acquisition efforts relative to design and/or construction of PPRTA 2 (2015-2024) projects for El Paso County Department of Public Works. A complete list of project specific property acquisition statuses is included as well.

  • 7 Projects – property acquisition COMPLETE
  • 5 Projects – property acquisition IN PROGRESS
  • 1 Project – scope of work does not require property acquisition (Stapleton Drive/Briargate Parkway)
Project NameStatus of ProjectStatus of Property AcquisitionTotal Number of Parcel Acquisitions Required for ProjectTotal Number of Parcel Acquisitions Still Pending NegotiationTotal Number of Parcels Acquired by Eminent Domain (Condemnation)Total Number of Parcels DonatedTarget to Complete all AcquisitionsTotal Acquisition Cost to Date (Does not include Consultant fees)
Beacon Lite RoadProperty AcquisitionIn progress316203rd Quarter 2024 $         1,043,025.00
Black Forest Road (joint w/ City of Colorado Springs)City of Colorado Springs Led Project
Deer Creek, Base Camp, Microscope Way (aka Emigrant)DesignIn progress212100  $                               –  
Eastonville RoadDesignIn progressTBDTBD00  $                               –  
Fontaine Blvd/Security Blvd/Widefield Blvd IntersectionDesignComplete6000Complete $               15,150.00
Highway 105 
  Project A – Interstate 25 to Lake Woodmoor DrConstructionComplete16000Complete $         2,381,213.00
  Project B – Lake Woodmoor to MartingaleDesignNot StartedTBDTBDTBDTBD  
Main St/Security BlvdConstructionComplete00000 $                               –  
Old Meridian/McLaughlin RoundaboutConstructionComplete20002  $             427,748.00
Mesa Ridge ParkwayDesignIn progress109011st Quarter 2024 $                               –  
Monument Hill RoadComplete (2018)Complete11001  $             104,500.00
New Meridian/US 24 Int.ConstructionComplete17000Complete $             914,220.00
South Academy BlvdConstructionComplete1000Complete $                               –  
Stapleton Drive/Briargate Blvd Corridor Study (joint w/ City of Colorado Springs)N/AN/AN/AN/AN/AN/AN/AN/A
Tutt Blvd Extension (joint w/ City of Colorado Springs)City of Colorado Springs Led Project
West Colorado Avenue (joint w/ City of Manitou Springs/City of Colorado Springs)Complete (2021)In progress104122TBD $         3,061,721.44