Board of Directors – September 11, 2024: Quarterly Reports From Member Governments – El Paso County 2024 Second Quarter Report – Security Boulevard & Main Street Intersection Improvements

Project Description

Intersection improvements at the intersection of Security Boulevard & Main Street.  The intersections are currently equipped with traffic control devices that are more than three decades old with leaning traffic poles, inadequate signal head clearance, and exposed cabling.  Improvements will include the installation of new traffic signals and accompanying equipment, as well as new signage, striping, and pedestrian improvements. Improvements will update intersection operational efficiency, increase pedestrian and ADA access, and increase overall public safety.

Aerial map of Security Boulevard and Main Street

Vicinity Map

Project Team

  • Designer: El Paso County Engineering
  • Contractor: Sturgeon Electric Inc.
  • CM: FHU Engineering
Street level view of Security Boulevard and Main Street

New Signal Poles and Roadway at Security & Main Intersection

Cost Summary

  • PPRTA Budget: $750,000

Schedule Summary

  • Design: 2019 to 2021
  • Construction: 2023

Project Status

  • Advertised 4th Quarter 2022, began construction
  • Construction substantially complete (100% work complete, beginning closeout process)
    • Closeout will be fully completed upon completion of Security/Widefield & Fontaine Intersection Project as the two Projects were combined for Construction.
  • Ongoing coordination with CSU Electric for re-route of overhead electric related to new setup of traffic signal poles – existing OHE no longer needs to extend south of Main St and may be reduced to easement at northeast corner of intersection.