Board of Directors – September 11, 2024: Quarterly Reports From Member Governments – City of Colorado Springs 2024 Second Quarter Report – Trail Program

The City’s Parks, Recreation and Cultural Services (Parks) Department oversees trail improvement projects to include trail paving, capital corridor reconstruction, crossing improvements (at-grade and grade separated), drainage improvements, connectivity enhancements, and signage and related amenities. PPRTA provides funding for A-list Trail Programs as outlined in Table 8. These programs, like the Pikes Peak Greenway Corridor (PPG) Corridor Improvements, can consist of a single project or multiple projects. Parks looks for opportunities to leverage PPRTA funding to obtain grants to assist with overall project costs.

Table 8. Trail Projects

Project NameDescriptionStatus
Cottonwood Trail Corridor ImprovementsTrail constructed as part of the Academy at Cottonwood Creek Bridge replacement project.Completed
Midland Trail Improvements – Ridge Rd to Columbia St.Trail constructed with El Paso County’s A-list W. Colorado Avenue Reconstruction project.Completed
Pikes Peak Greenway (PPG) Corridor Improvements: 
Mesa Creek to Uintah StreetFuture installation of new concrete trail south of Mesa Road (contingent of some utility actions).The contractor for Colorado Springs Utilities has finished burying the power lines. The relocation of communication utilities and the removal of poles are also complete. Trail construction is anticipated to begin in Fall 2024.
Southwest Downtown Pedestrian Bridge Completed
Uintah St. UnderpassUnderpass at Uintah St. to allow PPG trail users grade separated crossing of street.Completed
Mesa Creek CrossingBridge over Mesa CreekCompleted installation of 800 linear feet of concrete trail and a 90-foot pedestrian bridge in March 2024
Rockrimmon at I-25 to Cottonwood CreekLeveraged PPRTA funds to reconstruction this trail segment with grant funding.Completed
Rock Island Trail Corridor ImprovementsPPRTA funds used for local match to grant funds ($766k) to construct the trail from Sand Creek (near Powers Blvd) to Constitution. Construction anticipated in late 2024/spring 2025. Non-PPRTA funded construction underway from Van Buren to Templeton Gap.Templeton Gap Road to Shooks Run: complete. Shooks Run to Van Buren Street: trail construction underway.
Wall construction complete.
Shooks Runs Trail Corridor ImprovementsTrail reconstruction preliminary design complete from E. Las Vegas to Pike Peak Greenway (PPG). Design pending from south of Fountain to Las Vegas St. Design for trail reconstruction started from Las Vegas St to PPG.Waiting to acquire needed property, easements and/or permissions from pertinent landowners.
Sinton Trail Corridor ImprovementsConcrete paving and associated improvements.The TOPS-funded segment of new trail from 30th street to Arrowswest along Garden of the Gods Rd was completed in March 2023. Other trail segment improvements have completed engineering, pending City review, and construction is pending staff availability.
Templeton Gap Trail Corridor ImprovementsConcrete paving and associated improvements.Trail crossing improvements at Union Blvd are complete. Bridge deck replacement near Mark Dabling intersection is complete as of July 2024. If additional funding is available, install concrete paving and associated improvements   from Mark Dabling to Union Blvd.

Figure 41: Construction complete for Mesa Creek Confluence Pedestrian Bridge.

Completed pedestrian bridge at Mesa Creek confluence

Figure 42: Rock Island Retaining wall and trail construction west of Cascade Underpass.

New retaining wall along the Rock Island trail underneath Cascade Avenue

Figure 43. Templeton Gap Bridge Redecking.

Newly redecked Templeton Gap pedestrian bridge