Current Phase: Construction
Construction Start Date: September 2022
Anticipated Completion Date: December 2024
Project Description: Academy Boulevard between Bijou Street and Airport Road is a six-lane road with poor pavement and with curb, gutter, and median conditions requiring replacement. Poor drainage is contributing to pavement decline, so a new storm water system is being designed to alleviate ponding issues. Planned improvements incorporate recommendations from the Great Streets Corridor Study, including a 10-foot-wide multi-use path. The project length of 4,700 feet includes full depth reclamation paving, a new 24” waterline, and intersection improvements.
Figure 6: New driveway on the east side of Academy Blvd.

Figure 7: Installation of a 42” sewer line

Budget
| Funding Source | Estimated Project Cost1 | Obligated | Spent to Date (Actual) | Percent Spent to Date2 |
|---|---|---|---|---|
| PPRTA | $15,985,734 | $15,700,609 | $8,756,762 | 56% |
| CSU | $3,129,323 | $3,129,323 | $266,797 | 9% |
| Total | $19,115,057 | $18,829,932 | $9,023,559 | 48% |
- Estimated project cost includes future anticipated funding authorization. Total project cost includes known work for project life-cycle phases from planning to construction completion.
- Actual funds spent of the current obligated amount.
Highlights:
- Installation of 12” waterline and 42” sewer line in Airport Road.
- Installation of various storm drains.
- Full depth reclamation of existing roadway structural section.
- Paved the east side of Academy between Airport Road and Pikes Peak.
- Placing new sidewalk, curb, and gutter.