Logo of the Pikes Peak Rural Transportation Authority with the tagline Promises Made, Promises Kept

719-471-7080

Board of Directors – September 11, 2024: City of Colorado Springs Monthly Change Order & Property Acquisition Report

September 2024 City of Colorado Springs Capital Change Order Log

Contract #ContractorProject  Title & Type of ServicesCity/TransitCO #Description of COAmt of COCurrent Contract TotalTotal Change OrdersOrig Contract AmountNew Contract Amount
T-11808SEMA ConstructionTempleton Gap Trail Bridge ReplacementCity1Add funds and ext to 12/31/24$25,423.92$329,039.42$25,423.92$329,039.42$354,463.42

September 2024 City of Colorado Springs Maintenance Change Order Log

Contract #ContractorProject  Title & Type of ServicesCity/TransitCO #Description of COAmt of COCurrent Contract TotalTotal Change OrdersOrig Contract AmountNew Contract Amount
T010429Advanced Traffic ProductsTraffic Control EquipmentCity3Exercise Option Year & Add Funds$300,000.00$900,000.00$600,000.00$300,000.00$1,200,000.00
T-11480AM Signal, LLCFLIR CameraCity1Exercise Option Year & Add funds$200,000.00$200,000.00$200,000.00$200,000.00$400,000.00

September 2024 City of Colorado Springs Task Order Log

Contract NumberTask Order NumberMod NumberTotal PriceVendorDescription and Type of ServiceMonthCity/TransitCapital MaintPPRTA Account Number
T-110642024-0011$372,591.11HCDOn-Call & ADA Concrete – ConstructionJulyCityMaint03-30-5233000
T-116192024-0031$35,511.00AbilityAlsace Way over Cheyenne Creek – ConstructionJulyCityMaint03-30-5205000
R0101022024-003 $38,316.00OlssonW Colorado Ave Striping Plans & AnalysisJulyCityCapital03-20-5030047
T-118722024-0011$324,804.87A-1PPRTA Chip Seal ProgramJulyCityMaint03-30-5231000
T-110892024-001 $175,000.00Myers ConstructionTruncated Domes – constructionAugustCityMaint03-30-5233000
T-116132024-001 $148,731.90Lucky DogDowntown Terminal (DTT) Truncated Domes – constructionAugustTransitCapital02-20-5020003
T-110672024-0013$566,909.52Concrete ExpertsPPRTA On Call & ADA ConcreteAugustCityMaint03-30-5233000
T-110632024-0012$665,306.97Eagle’s ViewPPRTA On Call & ADA ConcreteAugustCityMaint03-30-5233000
T-110652024-0012$578,152.87Lucky DogPPRTA On Call & ADA ConcreteAugustCityMaint03-30-5233000
T-110682024-0013$916,839.14ICSPPRTA On Call & ADA ConcreteAugustCityMaint03-30-5233000
T-116172024-012 $26,932.00AdarandStetson Hills over Sand CreekAugustCityMaint03-30-5205000
T-116172024-012 $26,226.75SchanelColo Ave Stair Fix – constructionAugustCityMaint03-30-5205000
R-110302024-0011$39,533.48Precision Concrete CuttingPPRTA SVDM – constructionAugustCityMaint03-30-5231000
T-118722024-0012$696,474.00A-1PPRTA Chip Seal ProgramAugustCityMaint03-30-5231000

July 2024 City of Colorado Springs Real Estate Services

Document NameReception No.Date Recording / ClosingProject NamePEA Amount 1099-$TCE Amount 1099-MiscImprovement / Damages / RoundingAdministrative SettlementTotal Amount PaidFunding SourceRES File No.
Temporary Construction Easement2240548437/17/2024S. Nev/St Elmo & Ramona Ave. Signal Design-Circle S Motel – TCE-2$218.40$701.60$780.00$1,700.00PPRTA20740
Grant of Public Improvement Easement2240591437/31/2024South Academy Blvd Reconstruction – Fountain to Jet Wing – 48 – SRI Real Estate Properties $53,447.00$6,307.00$10,000.00$71,100.00PPRTA20452
Temporary Construction Easement2240591447/31/2024South Academy Blvd Reconstruction – Fountain to Jet Wing – 48 – SRI Real Estate Properties $1,346.00PPRTA20452