To:
- Pikes Peak Rural Transportation Authority (PPRTA) Board of Directors
- Pikes Peak Rural Transportation Authority Citizen Advisory Committee (CAC)
From: City of Colorado Springs – Ryan Phipps, PE, Capital Improvements Manager
CC: City of Colorado Springs – Gayle Sturdivant, PE, PMP, City Engineer/ Deputy Public Works Director
Date: September 4, 2024
CONTRACT
Project: 2024 PPRTA Pedestrian and School and Neighborhood Pedestrian Improvements (PPRTA Capital Project No. 03-20-5030046 & 03-20-5030048)
Contract Amount: PPRTA: $199,995.00, Other: $0
Type: (Choose all that apply)
- ☒ Capital
- ☐ Maintenance
- ☐ Transit
- ☒ Consultant
- ☐ Equipment
- ☐ Construction
- ☐ Materials
- ☐ Personnel
- ☐ Other (description)
Project Description: Pedestrian Improvements Citywide and School and Neighborhood Pedestrian Improvements are PPRTA-funded capital programs (referred to as the Sidewalk Infill Program) that install missing sidewalk segments at various locations throughout the City of Colorado Springs.
In 2019, the City issued an RFP for on call Construction Management Services. As a result of that solicitation, FHU was awarded an on-call contract to provide Construction Management services.
FHU was selected to provide Construction Management Services for the Sidewalk Infill Program in 2024, which is focused on Cheyenne Blvd and Cheyenne Rd. The City is installing new sidewalk, safe pedestrian crossings, and replacing signals at two intersections. The initial task order with FHU to provide the Construction Management services for approximately the first six months of 2024 was executed for $199,995. This task order modification will extend the scope of services through the end of the year.
The City requests the PPRTA Board approve this task order modification with FHU for $199,995.00.
VENDOR INFORMATION
Vendor: FHU
Contract No.: R010080
Contract Term (start/end dates) / Duration: 1/1/2024-12/31/2024
FINANCIAL INFORMATION
| Budget Category | Project Category | Task Order Amount | Funds Available | 2024 Budget Amount | Budget Code |
|---|---|---|---|---|---|
| Pedestrian Improvements Citywide Ph. I | ☒ Capital ☐ Maintenance ☐ Transit | $100,000 | $119,963 | $687,000 | 03-20-5030046 |
| School and Neighborhood Pedestrian Imps | ☒ Capital ☐ Maintenance ☐ Transit | $99,995 | $129,509 | $412,000 | 03-20-5030048 |
AWARD PROCESS
- ☐ IFB (Invitation for Bid)
- ☒ RFP (Request for Proposal)
- ☐ Sole Source
- ☐ Other
Comments: R010080