Board of Directors – October 9, 2024: City of Colorado Springs Monthly Change Order & Property Acquisition Report

October 2024 City of Colorado Springs Capital Change Order Log

Contract #ContractorProject  Title & Type of ServicesCity/TransitChange Order #Description of Change OrderAmount of Change OrderCurrent Contract TotalTotal Change OrdersOriginal Contract AmountNew Contract Amount
none

October 2024 City of Colorado Springs Maintenance Change Order Log

Contract #ContractorProject  Title & Type of ServicesCity/TransitChange Order #Description of Change OrderAmount of Change OrderCurrent Contract TotalTotal Change OrdersOriginal Contract AmountNew Contract Amount
none

October 2024 City of Colorado Springs Task Order Log

Contract NumberTask Order NumberMod NumberTotal PriceVendorDescription and Type of ServiceMonthCity/TransitCapital / MaintenancePPRTA Account Number
T-116172024-014 $450.00Schanel ConstructionCache La Poudre Pedestrian Bridge – PaintingAugustCityMaintenance03-30-5205000
R0100762023-0022$47,300.00Dewberry EngineersBridge Scour Analysis – Structures – EngineeringAugustCityCapital03-20-5205000
R0101112024-0021$7,605.00StantecTutt Blvd Extension CM ServicesAugustCityCapital03-20-5030030
R0100842023-0062$14,450.00Granite Engineering GroupBridge Maintenance Material Testing ServicesAugustCityMaintenance03-30-5205000
T-116132024-002 $7,733.94Lucky Dog8th/Abbott Bus Stop Improvement SID: 477 – constructionAugustTransitCapital02-20-5020003
T-116132024-003 $7,617.47Lucky DogSidewalk Repair for 1015 Transit Dr. AugustTransitCapital02-20-5020003
T-116132024-004 $52,977.17Lucky DogCitadel Transfer Station ADA Pedestrian Ramp – ConstructionAugustTransitCapital02-20-5020003
R0101242024-0011$20,200.00Wilson & CompanyFalcon Estates & Hopeful NTMP Design SupportAugustCityCapital03-20-5030047
R0100802022-0042$1,005.00FHUPedestrian Crossing Standards Development – DesignAugustCityCapital03-20-5030047
T-116172024-016 $20,640.18Schanel ConstructionPikes Peak Greenway over Monument Creek – ConstructionSeptemberCityMaintenance03-30-5205000
T-116182024-008 $10,000.00WildcatRR Bridge Removal over Costilla Street – ConstructionSeptemberCityMaintenance03-30-5205000
T-111222024-0011-$27,363.53A-1 ChipsealSlurry Seal Maintenance – ConstructionSeptemberCityMaintenance03-30-5231000
R0100612024-0011$135,515.16Benesch8th Street over Fountain Creek Widening – DesignSeptemberCityMaintenance03-30-5205000
R0100802023-0031$208,400.00FHU11th and 10th Street Drainage – DesignSeptemberCityMaintenance03-30-5205000
R-116732024-0051$1,478.15Even PreisserMontebello Raised Crossing – ConstructionSeptemberCityMaintenance03-30-5208000
T-116172024-016 $222,839.65Schanel ConstructionEdison over West Fork Sand Creek – ConstructionSeptemberCityMaintenance03-30-5205000
T-116172024-009 $429,903.00WildcatEl Paso over Platte Bridge Removal – ConstructionSeptemberCityMaintenance03-30-5205000
T0103622024-0011$200,000.00Seal Coat SolutionsCrack Seal ProgramSeptemberCityMaintenance03-30-5231000
T0097342024-012 $9,835.24AdarandN Carefree over Templeton Gap Drainage – ConstructionSeptemberCityMaintenance03-30-5205000
R0100872023-0101$49,827.00HDR EngineeringFederal Grant Support & PreparationSeptemberCityMaintenance03-30-5208000
R0101022024-004 $42,101.00OlssonI25 & Garden of Gods Fence Design PlansSeptemberCityCapital03-20-5030044

City of Colorado Springs Real Estate Services

Document NameReception No.Date
Recording/
Closing
Project NameFee AmountPEA Amount
1099-S
TCE Amount
1099-Misc
Improvements / Damages /
Rounding
Administrative
Settlement
Total
Amount Paid
Funding
Source
RES File No.
Grant of Public Improvement Easement2240628478/13/2024South Academy Blvd Reconstruction – Fountain to Jet Wing – 33 – Hamilton, Robert $4,356.00 $755.00 $5,700.00PPRTA20442
Temporary Construction Easement2240628488/13/2024South Academy Blvd Reconstruction – Fountain to Jet Wing – 33 – Hamilton, Robert  $589.00  PPRTA20442
Quitclaim Deed2240632768/14/2024BNSF-North Nevada-Acquisition$3,100,000.00    $3,100,000.00PPRTA19117
Temporary Construction Easement2240678998/29/2024South Academy Blvd Reconstruction – Fountain to Jet Wing – 67 – US Government  $12,799.00$2,001.00 $14,800.00PPRTA20469