CONTRACT LIST
To:
- Pikes Peak Rural Transportation Authority – Citizen Advisory Committee for meeting on October 2, 2024
- Pikes Peak Rural Transportation Authority – Board of Directors for meeting on October 9, 2024
| Project Number | Project Name | Project Description | Contract / Change Order Amount | Vendor | Contract No. | Division | Maintenance, Capital, or Transit |
|---|---|---|---|---|---|---|---|
| 1 | Academy Blvd Reconstruction | Construction Services | PPRTA $28,581,059.61 CSU $419,142.16 Total $29,000,201.77 | AMES Construction | T – 10909 | City Engineering | Capital |
| 2 | Academy Blvd Reconstruction | Engineering Services | PPRTA $305,510.00 CSU $68,525.00 Total $374,035.00 | AECOM | T – 009337 | City Engineering | Capital |
| 3 | Circle Drive Bridges Replacement | Construction Management, Testing, and Inspection Services | $1,470,077.00 | Benesch | T – 10846 | City Engineering | Capital |
| 4 | Dublin Blvd Improvements | Engineering Services | $499,614.75 | Basis Partners | R010065 | City Engineering | Capital |
| 5 | Sidewalk Infill Program | Construction Services | $3,594,855.00 | Even Preisser, Inc | T009905 | City Engineering & Traffic Engineering | Capital |
| 6 | Tejon Revitalization | Construction Services | PPRTA $2,004,700.00 Other $5,240,633.00 Total $7,245,333.00 | Even Preisser, Inc | TBD | City Engineering & Traffic Engineering | Capital |
| 7 | Edge Lit Traffic Control Signs | Traffic Supplies | $200,000.00 | Traffic Signal Controls | T – 12086 | Traffic Engineering | Capital, Maintenance |
| 8 | Edge Lit Traffic Control Signs | Traffic Supplies | $200,000.00 | AM Signal | T – 12085 | Traffic Engineering | Capital, Maintenance |
| 9 | Edge Lit Traffic Control Signs | Traffic Supplies | $50,000.00 | Traffic & Parking Control | T – 12087 | Traffic Engineering | Capital, Maintenance |
| 10 | Rustic Hills – Halfmoon Paving | Construction Services | $482,608.25 | Elite Surface Infrastructure | R-11094 | O&M | Maintenance |
| 11 | Black Forest Rd Widening | Construction Management, Testing, and Inspection Services | $103,780.00 | Basis Partners | T – 010645 | City Engineering | Capital |
| 12 | Marksheffel Rd Improvements | Preconstruction coordination and ductbank installation | $1,011,191.37 | Kraemer North America | T – 11142 | City Engineering | Capital |