MEMORANDUM
DATE: July 10, 2024
TO: Pikes Peak RTA Citizen Advisory Committee and Board of Directors
FROM: Rick Sonnenburg, Program/Contracts Manager
SUBJECT: PIKES PEAK RTA–STAFF FIELD REVIEW REPORT-2024: 1st QUARTER
City of Colorado Springs
- Concrete (curbs, gutters, sidewalks, and pedestrian ramps) – Reviewed June 2024
See attachment - Hot-In Place Asphalt – Reviewed June 2024
- Rustic Hills Paving (signs OK)
- Chip Seal/Slurry Seal
- Overlays
- Signal Rebuilds
- New Signals
- Intersection Modifications
- Vehicles Purchased
- Bike Lanes
- Bridge Repair & Maintenance
- Metro Transit
- Capital Projects – Reviewed June 2024
- Black Forest Road (signs OK)
- Academy: Bijou to Airport Road (signs OK)
- Academy: Fountain to Proby Parkway (signs OK)
- Marksheffel-North (signs OK)
- Circle Drive Bridges (signs OK)
- El Paso Bridge over Fountain Creek (completed)
- South Cheyenne Bridges (completed)
- Galley Bridge over Sand Creek (signs OK)
- West Fillmore Bridge over Unnamed Channel (signs OK)
- I-25 Ramps: S. Nevada/Tejon (signs OK)
El Paso County
- Overlays
- Sidewalk/Curb/Gutter/Pedestrian Ramps – Reviewed June 2024
See attachment - Chip Seal Program
- Slurry Seal Program
- Bridges/Culverts
- Capital Projects
- Highway 105 (signs OK) – Reviewed June 2024
- Academy: I-25 to Bradley Road Ramps (signs OK)
City of Manitou Springs
- Overlays
- Chip Seal/Fog Seal
- Sidewalk/Curb/Gutter Pedestrian Ramps
- Bridge Repair & Maintenance
- Capital Project
Town of Green Mountain Falls
- Capital Project
Attachments
Additional Operations and Maintenance Data for PPRTA Staff
PPRTA On-call / ADA Detail
| Task ID | Address Number | Street | Intersecting Street | Location Description |
|---|---|---|---|---|
| 895930 | 4340 | WHISPERING CIR N | ||
| 895929 | 4340 | WHISPERING CIR N | Ped-Ramp | |
| 895924 | 4360 | WHISPERING CIR N | Ped-Ramp | |
| 895925 | 4360 | WHISPERING CIR N | ||
| 895919 | 4380 | WHISPERING CIR N | ||
| 895917 | 4390 | WHISPERING CIR N | ||
| 895914 | 4410 | WHISPERING CIR N | ||
| 895912 | 4420 | WHISPERING CIR N | ||
| 895907 | 4430 | WHISPERING CIR N | ||
| 895904 | 4440 | WHISPERING CIR N | ||
| 895902 | 4460 | WHISPERING CIR N | ||
| 895875 | 4510 | WHISPERING CIR N | Ped-Ramp | |
| 895931 | WHISPERING CIR N | BERMUDA CIR | Intersection – X-Pan | |
| 895927 | WHISPERING CIR N | WHISPERING CIR S | In front of 4360 Whispering Cir N – 1/2 X-Pan | |
| 895888 | WHISPERING CIR S | WHISPERING CT | Intersection – X-Pan | |
| 895897 | 4510 | WHISPERING CT | ||
| 2024 PPRTA Cost Share – HCD | ||||
| 892565 | 3945 | BUNK HOUSE DR WAGON MASTER DR | ||
| 888551 | 808 | E BOULDER ST | ||
| 888560 | 2620 | FAIRWAY DR | ||
| 892559 | 1603 | HOWARD AVE | ||
Program Status Reports: 2024 Maintenance Programs First Quarter
2024 Gravel Program
El Paso County crews completed 9.6 Lane Miles of gravel on Milne Rd, Holman Rd, Richardson Ln and Big Springs Rd in the First Quarter.

2024 Graveling

2024 Graveling
2024 Concrete Improvements Program
During the 1st quarter of 2024, work commenced on the 2023 Concrete Drainage Program. A total of 1,038 square yards of sidewalk, 4,313 linear feet of curb and gutter, 75 square yards of cross pan, 41 square yards of fillet, and 57 square yards of pedestrian ramps were completed. HCD completed 10% of the 2023 program totaling $512,818.76 at the following locations:
- Constitution Avenue.
- Hathaway Drive.
- 14328 White Peak Drive.
- 6701 Gelbvieh Road.
- 12272-12280 Chimney Smoke Drive.
- 9827 Everglades Drive.
- 2165 Allyn Way
- 7172 Boreal Drive.
- 7532 Calm Oasis Place.
- 3722 Sonoran Drive.
- 7260 River Bend Road.
- 169 Ithaca Street.
- 4020 Allgood Drive.
- 7134 Dutch Loop
- 4399-4415 East Anvil Drive.
- 162 Judson Street.
- 4458 Mcgrew Circle.
- 97 Suzanne Circle.
- 6770 Fielding Circle.
- Palmer Park Drainage project
- Western Drive. – Peterson Road. to
- Galley Road.
- Windmill Creek Way 4449
- Winged Foot Road. 9425
- Witches Hollow Lane. 4850