Board of Directors – July 10, 2024: Draft 2024 PPRTA Amended Budget – City of Colorado Springs

DATE: May 24, 2024

TO:

  • Pikes Peak Rural Transportation Authority (PPRTA) Board of Directors
  • Pikes Peak Rural Transportation Authority Citizen’s Advisory Committee (CAC)

FROM:

  • Gayle Sturdivant, Acting Public Works Director/City Engineer
  • Lan Rao, Transit Services Division Manager
  • Ryan Phipps, Capital Improvements Engineering Manager
  • Todd Frisbie, City Traffic Engineer
  • Corey Farkas, Operations and Maintenance Division Manager

RE: City of Colorado Springs Proposed 2024 Pikes Peak Rural Transportation Authority (PPRTA) Budget Amendment #1


The City of Colorado Springs is pleased to submit the proposed 2024 Budget Amendment #1 for the Capital Projects and Programs for 2015-2024 and 2005-2014, the Maintenance Program, and the Transit Program. Based on direction from PPRTA, this amendment will include additional 2023 revenue following the end of year financial close-out and projected additional revenue for 2024. The following table outlines the amounts available to allocate to City projects and programs.

CategoryAmount
Capital Projects & Programs$5,264,035
Maintenance Program$3,292,827
Transit Program (Net of fare revenue)$2,746,565
2024 Additional Budgeted Revenue 
Capital Projects & Programs$3,897,000
Maintenance Program$2,437,889
Transit Program$1,000,000

The following table restates the total available revenue considered in this amendment by program allocation:

Program Allocation for Amendment #1Amount
Capital Projects & Programs$9,161,035
Maintenance Program$5,730,716
Transit Program (Net of fare revenue)$3,746,565

Capital Projects and Programs Budget

The following table reflects the City’s requested budget capital allocations resulting from the 2024 Budget Amendment #1. The 2023 carryover amounts have been updated to reflect the actual carryover amounts, or allocated but unspent amounts, as provided by PPRTA. The total revised 2024 budget for the City’s capital projects and programs is $215,577,851.

The proposed capital projects and programs receiving additional budget in this amendment are summarized as follows:

  • Intersection Safety Improvements: Additional funds to address a variety of intersection safety issues throughout the city.
  • UPRR Mainline Over Fontanero Bridge Replacement: Additional funds for future construction.

2015-2024 Capital Projects and Program

Project Name2024 Initial Budget2023 Carryover (Unspent $)March 2024 Line Item Transfer2024 Budget Amendment #12024 Budget2024 Amended Budget with Carryover
8th St. Imps: Motor City Wav to Fountain Creek$1,000.000$3,164,672  $1,000,000$4,164,672
Academy Blvd: Bilou St. To Airport Rd. $10,450,258  $0$10,450,258
Academy Blvd: Fountain to Milton Proby Pkwy. $25,198,725  $0$25,198,725
Academy Over Cottonwood Creek Bridge Rehabilitation$13,300,000$0  $13,300,000$13,300,000
Airport Rd Over Spring Creek Bridge Replacement    $0$0
Barnes R. Roadway Improvements: Solar Ridge Dr To Powers Blvd    $0$0
Black Forest Rd: Woodmen to Research $9,567,956  $0$9,567,956
Centennial Blvd. Extension: Fillmore to Fontanero $468,009  $0$468,009
Centennial St: Garden of The Gods to Fillmore $5,000  $0$5,000
Chestnut St Over S Douglas Creek Bridge    $0$0
Circle Dr Bridges Combined$59,595,436$30,015,657  $9,595,436$39,611,093
Dublin Rd: Bridle Pass Wav to Powers Blvd.    $0$0
El Paso Bridge Over Fountain Creek Tributary $732,854  $0$732,854
Enchanted Circle Over Sand Creek Tributary Bridge    $0$0
Galley Rd Over West Fork Sand Creek Bridge Replacement $4,302,498  $0$4,302,498
1-25 Ramps: South Nevada/ Tejon St. Corridor Improvements$7,561,497$666,182  $7,561,497$8,227,679
Las Vegas St/Rover UPRR Crossing Relocation$2,000,000$11,251,375  $2,000,000$13,251,375
Old Ranch Rd Improvements and Bridge Construction $3  $0$3
Pikes Peak Ave: Colorado to Printers Pkwv. $12,644  $0$12,644
Platte Ave Connection To 1-25 Study    $0$0
Platte Ave Corridor Improvement Study $19,139  $0$19,139
Platte Ave WB Over Sand Creek Bridge Replacement $87,949  $0$87,949
S Cheyenne Canyon Rd 1 Over Cheyenne Creek Bridge$831,607$1,969,249  $831,607$2,800,856
Shook’s Run Bridge Corridor Study $42,911  $0$42,911
Stapleton Dr /Briargate Blv. Corridor Study (Joint) $0  $0$0
Tutt Blvd Extension: Dublin to Templeton Gap Rd $3,702,344  $0$3,702,344
UPRR Mainline Over Fontanero Bridge Replacement$18,816,460$2,637,505-$10,000,000$8,661,035$17,477.495$20,115,000
UPRR Nevada & Tejon St. Crossing Reconstruction (Design Only)$1,000,000$1,244,023  $1,000,000$2,244,023
W Colorado Ave. Reconstruction: 31st St. to US24 $75,504  $0$75,504
W Fillmore Over Unnamed Channel Bridge Replacement $2,659,451  $0$2,659,451
Woodmen Road Improvements: Union CFI $227,279  $0$227,279
Capital Projects Subtotal$54,105,000$108,501,187-$10,000,000$8,661,035$52,766,035$161,267,222
TRAIL PROGRAMS      
Cottonwood Trail Corridor Improvements    $0$0
Midland Trail Improvements: Ridge Rd. To Columbia St.    $0$0
Pikes Peak Greenway Corridor Improvements $1,983,308  $0$1,983,308
Rock Island Trail Corridor Improvements $999,995  $0$999,995
Shook’s Run Trail Corridor Improvements $800,000  $0$800,000
Sinton Trail Corridor Improvements $520,852  $0$520,852
Templeton Gap Trail Corridor Improvements $575,000  $0$575,000
Trail Projects Subtotal$0$4,879,155$0$0$0$4,879,155
TRANSIT      
ADA-Paratransit Bus System Vehicle Replacement    $0$0
Fixed-Route Bus System Vehicle Replacement$1,081,000$4,234,998  $1,081,000$5,315,998
Sidewalk/Bus Slop Program Existing Routes$40,000$267,092  $40,000$307,092
Vanpool Vehicle Replacement    $0$0
Transit Subtotal$1,121,000$4,502,090$0$0$1,121,000$5,623,090
CAPITAL PROGRAMS      
Intersection Improvements Phase I$824,000$7,563,534 $500,000$1,324,000$8,887,534
On-Street Bikeway Improvements$412,000$906,862  $412,000$1,318,862
Pedestrian Transportation Improvements Phase I$687,000$1,173,983  $687,000$1,860,983
Roadway Safety and Traffic Operations Phase I$1,000,000$9,724,028$10,000,000 $11,000,000$20,724 028
School and Neighborhood Pedestrian Improvements$412,000$276,910  $412,000$688,910
Congestion and Incident Management Signal Improvement$412,000$815,876  $412,000$1,227,876
Traffic Signal System Upgrade (60 Locations) $602,270  $0$602,270
Companion Drainage Imps for Roadway Projects$412,000   $412,000$412,000
Emergency Bridge Fund$1,000,000$7,085,921  $1,000,000$8,085,921
Capital Programs Subtotal$5,159,000$28,149,384$10,000,000$500,000$15,659,000$43,808,384
TOTAL BUDGET$60,385,000$146,031,816$0$9,161,035$69,546,035$215,577,851

The 2024 Budget Amendment #1 requires a minor change to projects and programs in the 2005-2014 Capital Program. The 2023 carryover amounts have been updated to reflect the actual carryover amounts, or allocated but unspent amounts, as provided by PPRTA and shown in the table below. The 2024 budget included $264,000 in anticipated developer contribution but the actual amount was $269,906, creating an additional $5,906 to be included in Amendment #1.

2004-2014 Capital Projects and Programs

Project Name2024 Initial Budget2023 Carryover (Unspent $)2024 Budget Amendment #12024 Budget2024 Amended Budget with Carryover
Marksheffel (PAFB to Black Forest Road)$264,000$168$5,906$269,906$270,074

Remaining funds are obligated for the Marksheffel Rd from North Carefree to Dublin Blvd project.

Maintenance Program Budget

The proposed PPRTA Maintenance Program budget for 2024 has been increased from $37,859,895 to $58,738,641. This increase reflects the actual carryover (unspent) of $15,148,030 and both the 2023 revenue carryover of $3,292,827 and the 2024 additional projected revenue of $2,437,889 as reported by PPRTA.

2023 Maintenance Program Budget Summary

Project Name2024 Initial Budget2023 Carryover (Unspent $)2024 Budget Amendment #12024 Budget2024 Amended Budget with Carryover
Maintenance$37,859,895$15,148,030$5,730,716$43,590,611$58,738,641

The budget will address citywide maintenance needs such as capital project maintenance, bridge maintenance, and sign and signal maintenance. It will also fund roadway maintenance to include pavement overlays and rehabilitation, striping and patching, and concrete maintenance such as curb/gutter, sidewalk, and ADA pedestrian ramps in conjunction with the annual resurfacing program. Funds will also address retaining walls and other public structures within the right-of-way that may impede or jeopardize the traveling public. Additional maintenance needs will be identified through citizen requests and maintenance program evaluation processes.

Transit Program Budget

The PPRTA Transit Program budget for 2024 has been increased from $15,494,060 to $23,742,715. This increase reflects the carryover of $4,502,090 and both the 2023 revenue carryover of $2,746,565 and the 2024 additional projected revenue of $1,000,000 as reported by PPRTA.

Project Name2024 Initial Budget2023 Carryover (Unspent $)2024 Budget Amendment #12024 Budget2024 Amended Budget with Carryover
Transit$15,494,060$4,502,090$3,746,565$19,240,625$23,742,715

Additional information on the transit budget is provided in the attached memo.