Logo of the Pikes Peak Rural Transportation Authority with the tagline Promises Made, Promises Kept

719-471-7080

Board of Directors – July 10, 2024: City of Colorado Springs Monthly Change Order & Property Acquisition Report

July 2024 City of Colorado Springs Capital Change Order Log

Contract NumberContractorProject TitleCity or TransitChange Order NumberDescription  of Change OrderAmount of Change OrderCurrent Contract TotalTotal Change OrdersOriginal Contract AmountNew Contract Amount
T010322SEMA ConstructionCentennial Blvd ExtensionCity3Time extension to 7/31/24$0.00$18,654,439.94$3,930,803.94$14,723,636.00$18,654,439.94

July 2024 City of Colorado Springs Maintenance Change Order Log

Contract NumberContractorProject TitleCity or TransitChange Order NumberDescription  of Change OrderAmount of Change OrderCurrent Contract TotalTotal Change OrdersOriginal Contract AmountNew Contract Amount
T010734Pyramid24 & UnionCity3Reduce for contract closeout-$28,725.07$1,401,977.40$28,725.07$1,401,977.40$1,373,252.33

July 2024 City of Colorado Springs Task Order Log

Contract NumberTask Order NumberMod NumberTotal PriceVendorDescription and Type of ServiceMonthCity or TransitCapital or MaintenancePPRTA Account Number
T-110672024-0012$381,566.00Concrete ExpertsOn-Call & ADA Concrete – ConstructionMayCityMaintenance03-30-5233000
T-110652024-0011$391,333.00Lucky DogOn-Call & ADA Concrete – ConstructionMayCityMaintenance03-30-5233000
T-110682024-0012$445,808.00ICSOn-Call & ADA Concrete – ConstructionMayCityMaintenance03-30-5233000
T116172024-007 $5,400.00SchanelReturn Rd over Platte – InspectionMayCityMaintenance03-30-5205000
R0100762023-0021$69,848.00Dewberry EngineersBridge Scour Analysis – DesignMayCityMaintenance03-30-5205000
R0100692022-0042$29,078.40Jacobs EngineeringMonument Survey & Land PlatsJuneCityMaintenance03-30-5234000
R0100782023-0022$86,113.00ESTBridge Preventative Maintenance Design & Construction PlansJuneCityMaintenance03-30-5205000
T-116172024-008 $416,456.59Schanel ConstructionBeacon Street Culvert – ConstructionJuneCityMaintenance03-30-5205000
T-116172024-009 $12,240.80Schanel Construction31st Street Pedestrian Bridge RepairJuneCityMaintenance03-30-5205000
R0101062024-001 $25,002.31RockSolOn-Call CMJuneCityMaintenance03-30-5205000
T-116192024-004 $315,547.50AbilityArrowswest over South Douglas Creek – ConstructionJuneCityMaintenance03-30-5205000
T-116192024-005 $193,272.00AbilityDairy Ranch over Dry Creek-ConstructionJuneCityMaintenance03-30-5205000
R0100842023-0031$58,400.00Granite Engineering GroupAdd funds to complete material testingJuneCityMaintenance03-30-5232000

May 2024 City of Colorado Springs Real Estate Services

Document NameReception NumberDate
Recording/
Closing
Project NamePEA Amount
1099-S
TCE Amount
1099-Misc
Improvements/
Damages/
Rounding
Administrative
Settlement
Total
Amount Paid
Funding
Source
RES File Number
Grant of Public Improvement Easement2240376515/20/2024Chelton & Delta Traffic Signal – J H Foods LTD.$4,613.00 $3,287.00 $7,900.00PPRTA20541
Grant of Public Improvement Easement2240377055/20/2024South Academy Reconstruction Project-Fountain to Jet Wing – 56 – JH Foods Ltd$29,133.00 $4,073.00 $2,500.00$40,800.00PPRTA20460
Temporary Construction Easement2240377065/20/2024South Academy Reconstruction Project-Fountain to Jet Wing – 56 – JH Foods Ltd $5,094.00  PPRTA20460
Grant of Public Improvement Easement2240410215/31/2024South Academy Reconstruction Project-Fountain to Jet Wing-42-Gateway Commercial$200.00 $1,581.00$2,750.00 $10,000.00PPRTA20447
Grant of Public Improvement Easement2240410225/31/2024South Academy Reconstruction Project-Fountain to Jet Wing-43-Gateway Commercial$300.00   PPRTA20448
Grant of Public Improvement Easement2240410235/31/2024South Academy Reconstruction Project-Fountain to Jet Wing-44-Gateway Commercial$287.00   PPRTA20449
Temporary Construction Easement2240410245/31/2024South Academy Reconstruction Project-Fountain to Jet Wing-42 & 42A-Gateway Commercial $1,027.00  PPRTA20447
Temporary Construction Easement2240410255/31/2024South Academy Reconstruction Project-Fountain to Jet Wing-43-Gateway Commercial $1,749.00  PPRTA20448
Temporary Construction Easement2240410265/31/2024South Academy Reconstruction Project-Fountain to Jet Wing-44-Gateway Commercial $2,106.00  PPRTA20449