2025 Annual Report – PPRTA-2 Project Schedule: El Paso County

Table showing the capital project schedule for El Paso County PPRTA projects from 2025 to 2027

Title

Capital Project Schedule in El Paso County

Alternate Text for Image Description

Table showing the capital project schedule for El Paso County PPRTA projects from 2022 to 2025

Text Version

The chart shows the project schedule projections for El Paso County’s PPRTA projects.

  1. Beacon Lite Road: Highway 105 to County Line
    • Design: Quarter one of 2022 through quarter three of 2024
    • Construction: Entire year of 2025
  2. Black Forest Road Roadway Improvements: Woodmen Road to Research Parkway
    • City of Colorado Springs Led Project
  3. Deer Creek, Base Camp, Emigrant: Monument Hill to Woodmoor
    • Design: Quarter one of 2022 through quarter two of 2025
    • Construction: Quarters three and four of 2025
  4. Eastonville Road: McLaughlin to Latigo
    • Design: Quarter one of 2022
    • Construction: Quarters three and four of 2025
  5. Fontaine Boulevard at Security Boulevard and Widefield Boulevard
    • Design: Quarter one of 2022
    • Construction: Quarter two of 2022 through quarter one of 2025
  6. Highway 105:
    • Interstate 25 to Lake Woodmoor
      • Design: Quarter one of 2022 through first quarter of 2023
      • Construction: Second quarter of 2023 through first quarter of 2025
    • Lake Woodmoor to Highway 83
      • Design: Quarter one of 2022 through quarter second of 2025
      • Construction: Third and fourth quarters of 2025
  7. Main Street at Security Boulevard: Complete
  8. Meridian / McLaughlin Roundabout: Complete
  9. Mesa Ridge Parkway Improvements: Powers Boulevard to Marksheffel Road
    • Design: Quarter one of 2022 through quarter four of 2024
    • Construction: Quarters one through four of 2025
  10. Monument Hill Road: County Line Road to Woodmoor Road: Complete
  11. New Meridian at U.S. Highway 24: Substantially Complete
  12. South Academy Boulevard: Interstate 25 to Bradley Road Ramps
    • Design: Quarter one of 2022 through quarter two of 2023
    • Construction: Quarter three of 2023 through quarter four of 2025
  13. Stapleton Drive / Briargate Boulevard Corridor Study (Joint Project): Complete
  14. Tutt Boulevard Extension: Dublin Boulevard to Templeton Gap Road (Joint Project)
    • City of Colorado Springs Led Project
  15. West Colorado Avenue Reconstruction: 31st Street to U.S. Highway 24 (Joint Project): Complete